Wastewater treatment facilities; grant to Cities of Lynchburg and Richmond for CSO control projects. (SB1095)

Introduced By

Sen. Emmett Hanger (R-Mount Solon)

Progress

Introduced
Passed Committee
Passed House
Passed Senate
Signed by Governor
Became Law

Description

Bond issuance for wastewater treatment facilities. Authorizes the Virginia Public Building Authority to issue an additional $150 million in bonds to continue installing nutrient removal technology in eligible wastewater treatment facilities to comply with the Chesapeake Bay TMDL and the Watershed Implementation Plan. These funds would complete projects at facilities under existing signed Water Quality Improvement Fund agreements and at additional eligible facilities that did not receive moneys from the original bonds issued in 2007. Read the Bill »

Outcome

Bill Has Failed

History

DateAction
01/09/2013Prefiled and ordered printed; offered 01/09/13
01/09/2013Prefiled and ordered printed; offered 01/09/13 13101579D
01/09/2013Referred to Committee on Finance
01/21/2013Impact statement from DPB (SB1095)
01/23/2013Reported from Finance with substitute (14-Y 0-N) (see vote tally)
01/23/2013Committee substitute printed 13104426D-S1
01/24/2013Constitutional reading dispensed (39-Y 0-N) (see vote tally)
01/25/2013Read second time
01/25/2013Reading of substitute waived
01/25/2013Committee substitute agreed to 13104426D-S1
01/25/2013Engrossed by Senate - committee substitute SB1095S1
01/28/2013Impact statement from DPB (SB1095S1)
01/28/2013Read third time and passed Senate (40-Y 0-N) (see vote tally)
02/02/2013Placed on Calendar
02/02/2013Read first time
02/02/2013Referred to Committee on Appropriations
02/04/2013Assigned App. sub: Economic Development, Agriculture and Natural Resources
02/11/2013Subcommittee recommends laying on the table
02/18/2013Left in Appropriations