Electric utilities, certain; updated integrated resource plans. (HB2244)

Introduced By

Del. Matthew James (D-Portsmouth)

Progress

Introduced
Passed Committee
Passed House
Passed Senate
Signed by Governor
Became Law

Description

Electric utilities; integrated resource plans. Requires electric utilities serving two million or more customers in the Commonwealth to file an integrated resources plan (IRP) by September 1 of each year. Currently, they are required to file an IRP at least every two years. The measure requires copies of the IRP to be provided to the Chairmen of the House and Senate Committees on Commerce and Labor and to the chairman of the Commission on Electric Utility Regulation. The measure also requires that IRPs evaluate compliance options to minimize effects on customer rates of pending federal environmental rules. Amends § 56-599, of the Code of Virginia. Read the Bill »

Outcome

Bill Has Failed

History

DateAction
01/19/2015Committee
01/19/2015Presented and ordered printed 15103732D
01/19/2015Referred to Committee on Commerce and Labor
01/22/2015Assigned C & L sub: Special Subcommittee on Energy
01/22/2015Impact statement from SCC (HB2244)
02/03/2015Subcommittee recommends reporting (14-Y 0-N)
02/05/2015Reported from Commerce and Labor (21-Y 0-N) (see vote tally)
02/07/2015Read first time
02/09/2015Read second time and engrossed
02/10/2015Read third time and passed House (99-Y 0-N 1-A)
02/10/2015VOTE: PASSAGE (99-Y 0-N 1-A) (see vote tally)
02/11/2015Constitutional reading dispensed
02/11/2015Referred to Committee on Commerce and Labor
02/23/2015Stricken at request of Patron in Commerce and Labor (9-Y 0-N) (see vote tally)

Video