HB1451: Public school divisions; SCC to establish pilot program for schools generating electricity.


VIRGINIA ACTS OF ASSEMBLY -- CHAPTER
An Act to direct the State Corporation Commission to establish a pilot program for schools that generate electricity at levels that exceed the school's consumption.
[H 1451]
Approved

 

Be it enacted by the General Assembly of Virginia:

1. § 1. That the State Corporation Commission (the Commission) shall require a Phase II Utility as defined in subdivision A 1 of § 56-585.1 of the Code of Virginia to submit a proposal to the Commission to conduct a pilot program, not to exceed 10 megawatts in the aggregate, in its certificated service territory to allow any school in a public school division in the Commonwealth that generates electricity from a wind-powered or solar-powered renewable energy generation facility located at the school in amounts that exceed the amount of electricity consumed by the school in a billing period, at the option of the school board, to either (i) credit such excess electricity to the metered accounts of one or more other schools in the same public school division, as directed by the school board, in a manner that reduces the amount of electricity for which the other school or schools are billed and provides the other school or schools with a credit against the amount billed to the other school or schools, which credit shall be at the same rate that the school or schools would otherwise be charged for such amount of electricity, without the assessment by the supplier of any service charges or fees in connection with or arising out of such crediting or (ii) receive payment for such excess electricity from the electric utility at the contractually negotiated rate. The duration of any pilot program approved by the Commission pursuant to this act shall be six years.

2. That the State Corporation Commission shall, by December 1, 2018, adopt such rules or establish such guidelines as may be necessary for its general administration of the pilot program established under this act.

3. That any electric utility participating in the pilot program established under this act shall report to the General Assembly by December 1 of each year the pilot program is in effect, commencing in 2020, regarding the status of the pilot program's enrollment and any other information that may be appropriate.


HOUSE BILL NO. 1451
AMENDMENT IN THE NATURE OF A SUBSTITUTE
(Proposed by the Senate Committee on Commerce and Labor
on February 26, 2018)
(Patron Prior to Substitute--Delegate Sullivan)
A BILL to direct the State Corporation Commission to establish a pilot program for schools that generate electricity at levels that exceed the school's consumption.

Be it enacted by the General Assembly of Virginia:

1. § 1. That the State Corporation Commission (the Commission) shall require a Phase II Utility as defined in subdivision A 1 of § 56-585.1 of the Code of Virginia to submit a proposal to the Commission to conduct a pilot program, not to exceed 10 megawatts in the aggregate, in its certificated service territory to allow any school in a public school division in the Commonwealth that generates electricity from a wind-powered or solar-powered renewable energy generation facility located at the school in amounts that exceed the amount of electricity consumed by the school in a billing period, at the option of the school board, to either (i) credit such excess electricity to the metered accounts of one or more other schools in the same public school division, as directed by the school board, in a manner that reduces the amount of electricity for which the other school or schools are billed and provides the other school or schools with a credit against the amount billed to the other school or schools, which credit shall be at the same rate that the school or schools would otherwise be charged for such amount of electricity, without the assessment by the supplier of any service charges or fees in connection with or arising out of such crediting or (ii) receive payment for such excess electricity from the electric utility at the contractually negotiated rate. The duration of any pilot program approved by the Commission pursuant to this act shall be six years.

2. That the State Corporation Commission shall, by December 1, 2018, adopt such rules or establish such guidelines as may be necessary for its general administration of the pilot program established under this act.

3. That any electric utility participating in the pilot program established under this act shall report to the General Assembly by December 1 of each year the pilot program is in effect, commencing in 2020, regarding the status of the pilot program's enrollment and any other information that may be appropriate.


HOUSE BILL NO. 1451
AMENDMENT IN THE NATURE OF A SUBSTITUTE
(Proposed by the House Committee on Commerce and Labor
on February 8, 2018)
(Patron Prior to Substitute--Delegate Sullivan)
A BILL to direct the State Corporation Commission to establish a pilot program for schools that generate electricity at levels that exceed the school's consumption.

Be it enacted by the General Assembly of Virginia:

1. § 1. That the State Corporation Commission (the Commission) shall require a Phase II Utility as defined in subdivision A 1 of § 56-585.1 of the Code of Virginia to submit a proposal to the Commission to conduct a pilot program in its certificated service territory to allow a school in a public school division in the Commonwealth that generates electricity from a wind-powered or solar-powered renewable energy generation facility located at the school in amounts that exceed the amount of electricity consumed by the school in a billing period, at the option of the school board, to either (i) credit such excess electricity to the metered accounts of one or more other schools in the same public school division, as directed by the school board, in a manner that reduces the amount of electricity for which the other school or schools are billed and provides the other school or schools with a credit against the amount billed to the other school or schools, which credit shall be at the same rate that the school or schools would otherwise be charged for such amount of electricity, without the assessment by the supplier of any service charges or fees in connection with or arising out of such crediting or (ii) receive payment for such excess electricity from the electric utility at the corresponding retail rate. The duration of any pilot program approved by the Commission pursuant to this act shall be six years.

2. That the State Corporation Commission shall, by December 1, 2018, adopt such rules or establish such guidelines as may be necessary for its general administration of the pilot program established under this act.

HOUSE BILL NO. 1451

Offered January 17, 2018
A BILL to amend and reenact § 56-594 of the Code of Virginia, relating to net energy metering by schools.
Patron-- Sullivan

Committee Referral Pending

Be it enacted by the General Assembly of Virginia:

1. That § 56-594 of the Code of Virginia is amended and reenacted as follows:

§ 56-594. Net energy metering provisions.

A. The Commission shall establish by regulation a program that affords eligible customer-generators the opportunity to participate in net energy metering, and a program, to begin no later than July 1, 2014, for customers of investor-owned utilities and no later than July 1, 2015, for customers of electric cooperatives, to afford eligible agricultural customer-generators the opportunity to participate in net energy metering. The regulations may include, but need not be limited to, requirements for (i) retail sellers; (ii) owners or operators of distribution or transmission facilities; (iii) providers of default service; (iv) eligible customer-generators; (v) eligible agricultural customer-generators; or (vi) any combination of the foregoing, as the Commission determines will facilitate the provision of net energy metering, provided that the Commission determines that such requirements do not adversely affect the public interest. On and after July 1, 2017, small agricultural generators or eligible agricultural customer-generators may elect to interconnect pursuant to the provisions of this section or as small agricultural generators pursuant to § 56-594.2, but not both. Existing eligible agricultural customer-generators may elect to become small agricultural generators, but may not revert to being eligible agricultural customer-generators after such election. On and after July 1, 2019, interconnection of eligible agricultural customer-generators shall cease for electric cooperatives only, and such facilities shall interconnect solely as small agricultural generators. For electric cooperatives, eligible agricultural customer-generators whose renewable energy generating facilities were interconnected before July 1, 2019, may continue to participate in net energy metering pursuant to this section for a period not to exceed 25 years from the date of their renewable energy generating facility's original interconnection.

B. For the purpose of this section:

"Eligible agricultural customer-generator" means a customer that operates a renewable energy generating facility as part of an agricultural business, which generating facility (i) uses as its sole energy source solar power, wind power, or aerobic or anaerobic digester gas, (ii) does not have an aggregate generation capacity of more than 500 kilowatts, (iii) is located on land owned or controlled by the agricultural business, (iv) is connected to the customer's wiring on the customer's side of its interconnection with the distributor; (v) is interconnected and operated in parallel with an electric company's transmission and distribution facilities, and (vi) is used primarily to provide energy to metered accounts of the agricultural business. An eligible agricultural customer-generator may be served by multiple meters that are located at separate but contiguous sites, such that the eligible agricultural customer-generator may aggregate in a single account the electricity consumption and generation measured by the meters, provided that the same utility serves all such meters. The aggregated load shall be served under the appropriate tariff.

"Eligible customer-generator" means a customer that owns and operates, or contracts with other persons to own, operate, or both, an electrical generating facility that (i) has a capacity of not more than 20 kilowatts for residential customers and not more than one megawatt for nonresidential customers on an electrical generating facility placed in service after July 1, 2015; (ii) uses as its total source of fuel renewable energy, as defined in § 56-576; (iii) is located on the customer's premises and is connected to the customer's wiring on the customer's side of its interconnection with the distributor; (iv) is interconnected and operated in parallel with an electric company's transmission and distribution facilities; and (v) is intended primarily to offset all or part of the customer's own electricity requirements. In addition to the electrical generating facility size limitations in clause (i), the capacity of any generating facility installed under this section after July 1, 2015, shall not exceed the expected annual energy consumption based on the previous 12 months of billing history or an annualized calculation of billing history if 12 months of billing history is not available.

"Net energy metering" means measuring the difference, over the net metering period, between (i) electricity supplied to an eligible customer-generator or eligible agricultural customer-generator from the electric grid and (ii) the electricity generated and fed back to the electric grid by the eligible customer-generator or eligible agricultural customer-generator.

"Net metering period" means the 12-month period following the date of final interconnection of the eligible customer-generator's or eligible agricultural customer-generator's system with an electric service provider, and each 12-month period thereafter.

"Small agricultural generator" has the same meaning that is ascribed to that term in § 56-594.2.

C. The Commission's regulations shall ensure that (i) the metering equipment installed for net metering shall be capable of measuring the flow of electricity in two directions and (ii) any eligible customer-generator seeking to participate in net energy metering shall notify its supplier and receive approval to interconnect prior to installation of an electrical generating facility. The electric distribution company shall have 30 days from the date of notification for residential facilities, and 60 days from the date of notification for nonresidential facilities, to determine whether the interconnection requirements have been met. Such regulations shall allocate fairly the cost of such equipment and any necessary interconnection. An eligible customer-generator's electrical generating system, and each electrical generating system of an eligible agricultural customer-generator, shall meet all applicable safety and performance standards established by the National Electrical Code, the Institute of Electrical and Electronics Engineers, and accredited testing laboratories such as Underwriters Laboratories. Beyond the requirements set forth in this section and to ensure public safety, power quality, and reliability of the supplier's electric distribution system, an eligible customer-generator or eligible agricultural customer-generator whose electrical generating system meets those standards and rules shall bear all reasonable costs of equipment required for the interconnection to the supplier's electric distribution system, including costs, if any, to (a) install additional controls, (b) perform or pay for additional tests, and (c) purchase additional liability insurance.

D. The Commission shall establish minimum requirements for contracts to be entered into by the parties to net metering arrangements. Such requirements shall protect the eligible customer-generator or eligible agricultural customer-generator against discrimination by virtue of its status as an eligible customer-generator or eligible agricultural customer-generator, and permit customers that are served on time-of-use tariffs that have electricity supply demand charges contained within the electricity supply portion of the time-of-use tariffs to participate as an eligible customer-generator or eligible agricultural customer-generator. Notwithstanding the cost allocation provisions of subsection C, eligible customer-generators or eligible agricultural customer-generators served on demand charge-based time-of-use tariffs shall bear the incremental metering costs required to net meter such customers.

E. If Except as provided in subsection G, if electricity generated by an eligible customer-generator or eligible agricultural customer-generator over the net metering period exceeds the electricity consumed by the eligible customer-generator or eligible agricultural customer-generator, the customer-generator or eligible agricultural customer-generator shall be compensated for the excess electricity if the entity contracting to receive such electric energy and the eligible customer-generator or eligible agricultural customer-generator enter into a power purchase agreement for such excess electricity. Upon the written request of the eligible customer-generator or eligible agricultural customer-generator, the supplier that serves the eligible customer-generator or eligible agricultural customer-generator shall enter into a power purchase agreement with the requesting eligible customer-generator or eligible agricultural customer-generator that is consistent with the minimum requirements for contracts established by the Commission pursuant to subsection D. The power purchase agreement shall obligate the supplier to purchase such excess electricity at the rate that is provided for such purchases in a net metering standard contract or tariff approved by the Commission, unless the parties agree to a higher rate. The eligible customer-generator or eligible agricultural customer-generator owns any renewable energy certificates associated with its electrical generating facility; however, at the time that the eligible customer-generator or eligible agricultural customer-generator enters into a power purchase agreement with its supplier, the eligible customer-generator or eligible agricultural customer-generator shall have a one-time option to sell the renewable energy certificates associated with such electrical generating facility to its supplier and be compensated at an amount that is established by the Commission to reflect the value of such renewable energy certificates. Nothing in this section shall prevent the eligible customer-generator or eligible agricultural customer-generator and the supplier from voluntarily entering into an agreement for the sale and purchase of excess electricity or renewable energy certificates at mutually-agreed upon prices if the eligible customer-generator or eligible agricultural customer-generator does not exercise its option to sell its renewable energy certificates to its supplier at Commission-approved prices at the time that the eligible customer-generator or eligible agricultural customer-generator enters into a power purchase agreement with its supplier. All costs incurred by the supplier to purchase excess electricity and renewable energy certificates from eligible customer-generators or eligible agricultural customer-generators shall be recoverable through its Renewable Energy Portfolio Standard (RPS) rate adjustment clause, if the supplier has a Commission-approved RPS plan. If not, then all costs shall be recoverable through the supplier's fuel adjustment clause. For purposes of this section, "all costs" shall be defined as the rates paid to the eligible customer-generator or eligible agricultural customer-generator for the purchase of excess electricity and renewable energy certificates and any administrative costs incurred to manage the eligible customer-generator's or eligible agricultural customer-generator's power purchase arrangements. The net metering standard contract or tariff shall be available to eligible customer-generators or eligible agricultural customer-generators on a first-come, first-served basis in each electric distribution company's Virginia service area until the rated generating capacity owned and operated by eligible customer-generators, eligible agricultural customer-generators, and small agricultural generators in the state reaches one percent of each electric distribution company's adjusted Virginia peak-load forecast for the previous year, and shall require the supplier to pay the eligible customer-generator or eligible agricultural customer-generator for such excess electricity in a timely manner at a rate to be established by the Commission.

F. Any residential eligible customer-generator or eligible agricultural customer-generator who owns and operates, or contracts with other persons to own, operate, or both, an electrical generating facility with a capacity that exceeds 10 kilowatts shall pay to its supplier, in addition to any other charges authorized by law, a monthly standby charge. The amount of the standby charge and the terms and conditions under which it is assessed shall be in accordance with a methodology developed by the supplier and approved by the Commission. The Commission shall approve a supplier's proposed standby charge methodology if it finds that the standby charges collected from all such eligible customer-generators and eligible agricultural customer-generators allow the supplier to recover only the portion of the supplier's infrastructure costs that are properly associated with serving such eligible customer-generators or eligible agricultural customer-generators. Such an eligible customer-generator or eligible agricultural customer-generator shall not be liable for a standby charge until the date specified in an order of the Commission approving its supplier's methodology.

G. If an eligible customer-generator is a school in a public school division in the Commonwealth, then notwithstanding any provision of subsection E to the contrary, upon the request of the school board for the public school division, any electricity generated by such eligible customer-generator over the net metering period that is in excess of the amount of electricity consumed by such eligible customer-generator shall be credited to the metered accounts of one or more other schools in the same public school division, as directed by the school board, in a manner that reduces the amount of electricity for which the other school or schools are billed and provides the other school or schools with a credit against the amount billed to the other school or schools. The amount of the credit shall be calculated at the same rate that the school or schools would otherwise be charged for such amount of electricity, without the assessment by the supplier of any service charges or fees in connection with or arising out of such crediting. Such an eligible customer-generator shall not receive any other compensation from the supplier for the amount of excess electricity credited to any other school as provided in this subsection. This subsection shall not affect any agreement between such eligible customer-generator and the supplier with regard to ownership of renewable energy certificates associated with the electrical generating facility.