SB741: Stormwater management; termination of general permit, notice.
Be it enacted by the General Assembly of Virginia:
1. That the Code of Virginia is amended by adding a section numbered 62.1-44.15:26.1 as follows:
§ 62.1-44.15:26.1. Termination of Construction General Permit coverage.
A. A VSMP authority shall recommend that the Department of Environmental Quality terminate coverage under a General Permit for Discharges of Stormwater from Construction Activities (Construction General Permit) within 60 days of receiving a complete notice of termination from the operator of the construction activity.
B. Coverage under a Construction General Permit shall be deemed to be terminated 90 days after the receipt by the VSMP authority of a complete notice of termination from the operator of the construction activity.
C. If a VSMP authority receives a notice of termination of a Construction General Permit that it determines to be incomplete, the VSMP authority shall, within a reasonable time, inform the operator of the construction activity of such incompleteness and provide the operator with a detailed list itemizing the elements of information that are missing from the notice.
Be it enacted by the General Assembly of Virginia:
1. That the Code of Virginia is amended by adding a section numbered 62.1-44.15:26.1 as follows:
§ 62.1-44.15:26.1. Termination of Construction General Permit coverage.
A. A VSMP authority shall [ advise recommend
that ] the Department of Environmental Quality [ to
] terminate coverage under a General Permit for Discharges
of Stormwater from Construction Activities (Construction General Permit) within
60 days of receiving a complete notice of termination from the operator of the
construction activity.
B. Coverage under a Construction General Permit shall be deemed to be terminated 90 days after the receipt by the VSMP authority of a complete notice of termination from the operator of the construction activity.
C. If a VSMP authority receives a notice of termination of a Construction General Permit that it determines to be incomplete, the VSMP authority shall, within a reasonable time, inform the operator of the construction activity of such incompleteness and provide the operator with a detailed list itemizing the elements of information that are missing from the notice.
SENATE BILL NO. 741
Be it enacted by the General Assembly of Virginia:
1. That the Code of Virginia is amended by adding a section numbered 62.1-44.15:26.1 as follows:
§ 62.1-44.15:26.1. Termination of Construction General Permit coverage.
A. A VSMP authority shall advise the Department of Environmental Quality to terminate coverage under a General Permit for Discharges of Stormwater from Construction Activities (Construction General Permit) within 60 days of receiving a complete notice of termination from the operator of the construction activity.
B. Coverage under a Construction General Permit shall be deemed to be terminated 90 days after the receipt by the VSMP authority of a complete notice of termination from the operator of the construction activity.
C. If a VSMP authority receives a notice of termination of a Construction General Permit that it determines to be incomplete, the VSMP authority shall, within a reasonable time, inform the operator of the construction activity of such incompleteness and provide the operator with a detailed list itemizing the elements of information that are missing from the notice.