SB741: Stormwater management; termination of general permit, notice.


VIRGINIA ACTS OF ASSEMBLY -- CHAPTER
An Act to amend the Code of Virginia by adding a section numbered 62.1-44.15:26.1, relating to stormwater management; termination of general permit; notice.
[S 741]
Approved

 

Be it enacted by the General Assembly of Virginia:

1. That the Code of Virginia is amended by adding a section numbered 62.1-44.15:26.1 as follows:

§ 62.1-44.15:26.1. Termination of Construction General Permit coverage.

A. A VSMP authority shall recommend that the Department of Environmental Quality terminate coverage under a General Permit for Discharges of Stormwater from Construction Activities (Construction General Permit) within 60 days of receiving a complete notice of termination from the operator of the construction activity.

B. Coverage under a Construction General Permit shall be deemed to be terminated 90 days after the receipt by the VSMP authority of a complete notice of termination from the operator of the construction activity.

C. If a VSMP authority receives a notice of termination of a Construction General Permit that it determines to be incomplete, the VSMP authority shall, within a reasonable time, inform the operator of the construction activity of such incompleteness and provide the operator with a detailed list itemizing the elements of information that are missing from the notice.


SENATE BILL NO. 741
Senate Amendments in [ ] -- January 23, 2018
A BILL to amend the Code of Virginia by adding a section numbered 62.1-44.15:26.1, relating to stormwater management; termination of general permit; notice.
Patron Prior to Engrossment--Senator Ruff

Referred to Committee on Agriculture, Conservation and Natural Resources

Be it enacted by the General Assembly of Virginia:

1. That the Code of Virginia is amended by adding a section numbered 62.1-44.15:26.1 as follows:

§ 62.1-44.15:26.1. Termination of Construction General Permit coverage.

A. A VSMP authority shall  [ advise  recommend that  ] the Department of Environmental Quality  [ to   ] terminate coverage under a General Permit for Discharges of Stormwater from Construction Activities (Construction General Permit) within 60 days of receiving a complete notice of termination from the operator of the construction activity.

B. Coverage under a Construction General Permit shall be deemed to be terminated 90 days after the receipt by the VSMP authority of a complete notice of termination from the operator of the construction activity.

C. If a VSMP authority receives a notice of termination of a Construction General Permit that it determines to be incomplete, the VSMP authority shall, within a reasonable time, inform the operator of the construction activity of such incompleteness and provide the operator with a detailed list itemizing the elements of information that are missing from the notice.

SENATE BILL NO. 741

Offered January 10, 2018
Prefiled January 10, 2018
A BILL to amend the Code of Virginia by adding a section numbered 62.1-44.15:26.1, relating to stormwater management; termination of general permit; notice.
Patron-- Ruff

Referred to Committee on Agriculture, Conservation and Natural Resources

Be it enacted by the General Assembly of Virginia:

1. That the Code of Virginia is amended by adding a section numbered 62.1-44.15:26.1 as follows:

§ 62.1-44.15:26.1. Termination of Construction General Permit coverage.

A. A VSMP authority shall advise the Department of Environmental Quality to terminate coverage under a General Permit for Discharges of Stormwater from Construction Activities (Construction General Permit) within 60 days of receiving a complete notice of termination from the operator of the construction activity.

B. Coverage under a Construction General Permit shall be deemed to be terminated 90 days after the receipt by the VSMP authority of a complete notice of termination from the operator of the construction activity.

C. If a VSMP authority receives a notice of termination of a Construction General Permit that it determines to be incomplete, the VSMP authority shall, within a reasonable time, inform the operator of the construction activity of such incompleteness and provide the operator with a detailed list itemizing the elements of information that are missing from the notice.