A BILL to amend and reenact §§ 56-594 and 67-102 of the Code of Virginia and § 1 of the first enactment of Chapters 358 and 382 of the Acts of Assembly of 2013, as amended by Chapter 803 of the Acts of Assembly of 2017, and to amend the Code of Virginia by adding a section numbered 56-585.1:11, relating to the regulation of sales of electricity under third-party sales agreements; net energy; and the removal of other barriers to the increased implementation of distributed solar and other renewable energy in the Commonwealth.

Be it enacted by the General Assembly of Virginia:

1. That §§ 56-594 and 67-102 of the Code of Virginia are amended and reenacted and that the Code of Virginia is amended by adding a section numbered 56-585.1:11 as follows:

§ 56-585.1:11. Multi-family shared solar program.

A. As used in this section:

"Applicable bill credit rate" means the dollar-per-kilowatt-hour rate as defined in subsection D used to calculate a subscriber's bill credit. The applicable bill credit rate shall be set such that the shared solar program results in robust project development and shared solar program access for all customer classes.

"Bill credit" means the monetary value of the electricity, in kilowatt-hours, generated by the shared solar facility allocated to a subscriber to offset that subscriber's electricity bill.

"Investor-owned utility" means each investor-owned utility in the Commonwealth including, notwithstanding subsection G of § 56-580, any investor-owned utility whose service territory assigned to it by the Commission is located entirely within the Counties of Dickenson, Lee, Russell, Scott and Wise. "Investor-owned utility" does not include a Phase I Utility, as that term is defined in subdivision A 1 of § 56-585.1.

"Multi-family shared solar program" or "program" means the program created through the adoption of rules to allow for the development of shared solar facilities described in subsection C.

"Shared solar facility" means a facility that:

1. Generates electricity by means of a solar photovoltaic device with a nameplate capacity rating that does not exceed 3,000 kW alternating current at any single location or that does not exceed 5,000 kW alternating current at contiguous locations owned by the same entity or affiliated entities;

2. Is operated pursuant to a program whereby at least three subscribers receive a bill credit for the electricity generated from the facility in proportion to the size of their subscription;

3. Is located in the service territory of an investor-owned utility;

4. Is connected to the electric distribution grid serving the Commonwealth; and

5. Is located on a parcel of land on the premises of the multi-family utility customer or adjacent thereto.

"Subscriber" means a multi-family customer of an investor-owned electric utility that owns one or more subscriptions of a shared solar facility that is interconnected with the utility.

"Subscriber organization" means any for-profit or nonprofit entity that owns or operates one or more shared solar facilities. A "subscriber organization" shall not be considered a utility solely as a result of its ownership or operation of a shared solar facility.

"Subscription" means a contract or other agreement between a subscriber and the owner of a shared solar facility. A subscription shall be sized such that the estimated bill credits do not exceed the subscriber's average annual bill for the customer account to which the subscription is attributed.

B. The Commission shall establish by regulation a program that affords eligible multi-family customers of investor-owned utilities the opportunity to participate in shared solar projects. The regulations shall be adopted by the Commission by January 1, 2021.

C. An investor-owned utility shall provide a bill credit to a subscriber's subsequent monthly electric bill for the proportional output of a shared solar facility attributable to that subscriber. The shared solar program shall be administered as follows:

1. The value of the bill credit for the subscriber shall be calculated by multiplying the subscriber's portion of the kilowatt-hour electricity production from the shared solar facility by the applicable bill credit rate for the subscriber. Any amount of the bill credit that exceeds the subscriber's monthly bill shall be carried over and applied to the next month's bill in perpetuity;

2. The utility shall provide bill credits to a shared solar facility's subscribers for not less than 25 years from the date the shared solar facility becomes commercially operational;

3. The subscriber organization shall, on a monthly basis and in a standardized electronic format, provide to the investor-owned utility a subscriber list indicating the kilowatt-hours of generation attributable to each of the retail customers participating in a shared solar facility in accordance with the subscriber's portion of the output of the shared solar facility;

4. Lists may be updated monthly to reflect canceling subscribers and to add new subscribers. The investor-owned utility shall apply bill credits to subscriber bills within one billing cycle following the cycle during which the energy was generated by the shared solar facility;

5. The investor-owned utility shall, on a monthly basis and in a standardized electronic format, provide to the subscriber organization a report indicating the total value of bill credits generated by the shared solar facility in the prior month as well as the amount of the bill credit applied to each subscriber;

6. A subscriber organization may accumulate bill credits in the event that all of the electricity generated by a shared solar facility is not allocated to subscribers in a given month. On an annual basis, the subscriber organization shall furnish to the utility allocation instructions for distributing excess bill credits to subscribers; and

7. All environmental attributes associated with a shared solar facility, including renewable energy certificates, shall be considered property of the subscriber organization. At the subscriber organization's discretion, those attributes may be distributed to subscribers, sold to investor-owned utilities or other buyers, accumulated, or retired.

D. The Commission shall annually calculate the applicable bill credit rate as the effective retail rate of the customer's rate class, which shall be inclusive of all supply charges, delivery charges, demand charges, fixed charges, and any applicable riders or other charges to the customer. This rate shall be expressed in dollars or cents per kilowatt-hour.

E. The Commission shall establish by regulation a multi-family shared solar program by January 1, 2021, and shall require each investor-owned utility to file any tariffs, agreements, or forms necessary for implementation of the program. Any rule or utility implementation filings approved by the Commission shall:

1. Reasonably allow for the creation and financing of shared solar facilities;

2. Allow all customer classes to participate in the program, and ensure participation opportunities for all customer classes;

3. Not remove a customer from its otherwise applicable customer class in order to participate in a shared solar facility;

4. Reasonably allow for the transferability and portability of subscriptions, including allowing a subscriber to retain a subscription in a shared solar facility if the subscriber moves within the same utility territory;

5. Establish uniform standards, fees, and processes for the interconnection of shared solar facilities that allow the utility to recover reasonable interconnection costs for each shared solar facility;

6. Adopt standardized consumer disclosure forms;

7. Allow the investor-owned utilities to recover reasonable costs of administering the program;

8. Ensure nondiscriminatory and efficient requirements and utility procedures for interconnecting projects;

9. Address the colocation of two or more shared solar facilities on a single parcel of land, and provide guidelines for determining when two or more facilities are colocated; and

10. Include a program implementation schedule.

F. Within 180 days of finalization of the Commission's adoption of regulations for the shared solar program, utilities shall begin crediting subscriber accounts of each shared solar facility interconnected in its service territory.

§ 56-594. Net energy metering provisions.

A. The Commission shall establish by regulation a program that affords eligible customer-generators the opportunity to participate in net energy metering, and a program, to begin no later than July 1, 2014, for customers of investor-owned utilities and to begin no later than July 1, 2015, and to end July 1, 2019, for customers of electric cooperatives as provided in subsection G, to afford eligible agricultural customer-generators the opportunity to participate in net energy metering. The regulations may include, but need not be limited to, requirements for (i) retail sellers; (ii) owners or operators of distribution or transmission facilities; (iii) providers of default service; (iv) eligible customer-generators; (v) eligible agricultural customer-generators; or (vi) any combination of the foregoing, as the Commission determines will facilitate the provision of net energy metering, provided that the Commission determines that such requirements do not adversely affect the public interest. On and after July 1, 2017, small agricultural generators or eligible agricultural customer-generators may elect to interconnect pursuant to the provisions of this section or as small agricultural generators pursuant to § 56-594.2, but not both. Existing eligible agricultural customer-generators may elect to become small agricultural generators, but may not revert to being eligible agricultural customer-generators after such election. On and after July 1, 2019, interconnection of eligible agricultural customer-generators shall cease for electric cooperatives only, and such facilities shall interconnect solely as small agricultural generators. For electric cooperatives, eligible agricultural customer-generators whose renewable energy generating facilities were interconnected before July 1, 2019, may continue to participate in net energy metering pursuant to this section for a period not to exceed 25 years from the date of their renewable energy generating facility's original interconnection.

B. For the purpose of this section:

"Eligible agricultural customer-generator" means a customer that operates a renewable energy generating facility as part of an agricultural business, which generating facility (i) uses as its sole energy source solar power, wind power, or aerobic or anaerobic digester gas, (ii) does not have an aggregate generation capacity of more than 500 kilowatts, (iii) is located on land owned or controlled by the agricultural business, (iv) is connected to the customer's wiring on the customer's side of its interconnection with the distributor; (v) is interconnected and operated in parallel with an electric company's transmission and distribution facilities, and (vi) is used primarily to provide energy to metered accounts of the agricultural business. An eligible agricultural customer-generator may be served by multiple meters serving the eligible agricultural customer-generator that are located at separate but contiguous the same or adjacent sites, such that the eligible agricultural customer-generator may aggregate in a single account the electricity consumption and generation measured by the meters, provided that the same utility serves all such meters. The aggregated load shall be served under the appropriate tariff.

"Eligible customer-generator" means a customer that owns and operates, or contracts with other persons to own, operate, or both, an electrical generating facility that (i) has a capacity of not more than 20 25 kilowatts for residential customers and not more than one megawatt three megawatts for nonresidential customers on an electrical generating facility placed in service after July 1, 2015; (ii) uses as its total source of fuel renewable energy, as defined in § 56-576; (iii) is located on the customer's premises land owned or leased by the customer and is connected to the customer's wiring on the customer's side of its interconnection with the distributor; (iv) is interconnected and operated in parallel with an electric company's transmission and distribution facilities; and (v) is intended primarily to offset all or part of the customer's own electricity requirements. In addition to the electrical generating facility size limitations in clause (i), the capacity of any generating facility installed under this section after between July 1, 2015, and July 1, 2020, shall not exceed the expected annual energy consumption based on the previous 12 months of billing history or an annualized calculation of billing history if 12 months of billing history is not available. In addition to the electrical generating facility size limitation in clause (i), in the certificated service territory of a Phase I Utility, the capacity of any generating facility installed under this section after July 1, 2020, shall not exceed 100 percent of the expected annual energy consumption based on the previous 12 months of billing history or an annualized calculation of billing history if 12 months of billing history is not available, and in the certificated service territory of a Phase II Utility, the capacity of any generating facility installed under this section after July 1, 2020, shall not exceed 150 percent of the expected annual energy consumption based on the previous 12 months of billing history or an annualized calculation of billing history if 12 months of billing history is not available.

"Net energy metering" means measuring the difference, over the net metering period, between (i) electricity supplied to an eligible customer-generator or eligible agricultural customer-generator from the electric grid and (ii) the electricity generated and fed back to the electric grid by the eligible customer-generator or eligible agricultural customer-generator.

"Net metering period" means the 12-month period following the date of final interconnection of the eligible customer-generator's or eligible agricultural customer-generator's system with an electric service provider, and each 12-month period thereafter.

"Small agricultural generator" has the same meaning that is ascribed to that term in § 56-594.2.

C. The Commission's regulations shall ensure that (i) the metering equipment installed for net metering shall be capable of measuring the flow of electricity in two directions and (ii) any eligible customer-generator seeking to participate in net energy metering shall notify its supplier and receive approval to interconnect prior to installation of an electrical generating facility. The electric distribution company shall have 30 days from the date of notification for residential facilities, and 60 days from the date of notification for nonresidential facilities, to determine whether the interconnection requirements have been met. Such regulations shall allocate fairly the cost of such equipment and any necessary interconnection. An eligible customer-generator's electrical generating system, and each electrical generating system of an eligible agricultural customer-generator, shall meet all applicable safety and performance standards established by the National Electrical Code, the Institute of Electrical and Electronics Engineers, and accredited testing laboratories such as Underwriters Laboratories. Beyond the requirements set forth in this section and to ensure public safety, power quality, and reliability of the supplier's electric distribution system, an eligible customer-generator or eligible agricultural customer-generator whose electrical generating system meets those standards and rules shall bear all reasonable costs of equipment required for the interconnection to the supplier's electric distribution system, including costs, if any, to (a) install additional controls, (b) perform or pay for additional tests, and (c) purchase additional liability insurance.

D. The Commission shall establish minimum requirements for contracts to be entered into by the parties to net metering arrangements. Such requirements shall protect the eligible customer-generator or eligible agricultural customer-generator against discrimination by virtue of its status as an eligible customer-generator or eligible agricultural customer-generator, and permit customers that are served on time-of-use tariffs that have electricity supply demand charges contained within the electricity supply portion of the time-of-use tariffs to participate as an eligible customer-generator or eligible agricultural customer-generator. Notwithstanding the cost allocation provisions of subsection C, eligible customer-generators or eligible agricultural customer-generators served on demand charge-based time-of-use tariffs shall bear the incremental metering costs required to net meter such customers.

E. If electricity generated by an eligible customer-generator or eligible agricultural customer-generator over the net metering period exceeds the electricity consumed by the eligible customer-generator or eligible agricultural customer-generator, the customer-generator or eligible agricultural customer-generator shall be compensated for the excess electricity if the entity contracting to receive such electric energy and the eligible customer-generator or eligible agricultural customer-generator enter into a power purchase agreement for such excess electricity. Upon the written request of the eligible customer-generator or eligible agricultural customer-generator, the supplier that serves the eligible customer-generator or eligible agricultural customer-generator shall enter into a power purchase agreement with the requesting eligible customer-generator or eligible agricultural customer-generator that is consistent with the minimum requirements for contracts established by the Commission pursuant to subsection D. The power purchase agreement shall obligate the supplier to purchase such excess electricity at the rate that is provided for such purchases in a net metering standard contract or tariff approved by the Commission, unless the parties agree to a higher rate. The eligible customer-generator or eligible agricultural customer-generator owns any renewable energy certificates associated with its electrical generating facility; however, at the time that the eligible customer-generator or eligible agricultural customer-generator enters into a power purchase agreement with its supplier, the eligible customer-generator or eligible agricultural customer-generator shall have a one-time option to sell the renewable energy certificates associated with such electrical generating facility to its supplier and be compensated at an amount that is established by the Commission to reflect the value of such renewable energy certificates. Nothing in this section shall prevent the eligible customer-generator or eligible agricultural customer-generator and the supplier from voluntarily entering into an agreement for the sale and purchase of excess electricity or renewable energy certificates at mutually-agreed upon prices if the eligible customer-generator or eligible agricultural customer-generator does not exercise its option to sell its renewable energy certificates to its supplier at Commission-approved prices at the time that the eligible customer-generator or eligible agricultural customer-generator enters into a power purchase agreement with its supplier. All costs incurred by the supplier to purchase excess electricity and renewable energy certificates from eligible customer-generators or eligible agricultural customer-generators shall be recoverable through its Renewable Energy Portfolio Standard (RPS) rate adjustment clause, if the supplier has a Commission-approved RPS plan. If not, then all costs shall be recoverable through the supplier's fuel adjustment clause. For purposes of this section, "all costs" shall be defined as the rates paid to the eligible customer-generator or eligible agricultural customer-generator for the purchase of excess electricity and renewable energy certificates and any administrative costs incurred to manage the eligible customer-generator's or eligible agricultural customer-generator's power purchase arrangements. The net metering standard contract or tariff shall be available to eligible customer-generators or eligible agricultural customer-generators on a first-come, first-served basis in each electric distribution company's Virginia service area until the rated generating capacity owned and operated by eligible customer-generators, eligible agricultural customer-generators, and small agricultural generators in the Commonwealth reaches one six percent, in the aggregate, five percent of which is available to all customers and one percent of which is available only to low-income utility customers of each electric distribution company's adjusted Virginia peak-load forecast for the previous year (the systemwide cap), and shall require the supplier to pay the eligible customer-generator or eligible agricultural customer-generator for such excess electricity in a timely manner at a rate to be established by the Commission.

On and after the earlier of (i) 2024 for a Phase I Utility or 2025 for a Phase II Utility or (ii) when the aggregate rated generating capacity owned and operated by eligible customer-generators, eligible agricultural customer-generators, and small agricultural generators in the Commonwealth reaches three percent of a Phase I or Phase II Utility's adjusted Virginia peak-load forecast for the previous year, the Commission shall conduct a net energy metering proceeding.

In any net energy metering proceeding, the Commission shall, after notice and opportunity for hearing, evaluate and establish (a) an amount customers shall pay on their utility bills each month for the costs of using the utility's infrastructure; (b) an amount the utility shall pay to appropriately compensate the customer, as determined by the Commission, for the total benefits such facilities provide; (c) the direct and indirect economic impact of net metering to the Commonwealth; and (d) any other information the Commission deems relevant. The Commission shall establish an appropriate rate structure related thereto, which shall govern compensation related to all eligible customer-generators, eligible agricultural customer-generators, and small agricultural generators, except low-income utility customers, that interconnect after the effective date established in the Commission's final order. Nothing in the Commission's final order shall affect any eligible customer-generators, eligible agricultural customer-generators, and small agricultural generators who interconnect before the effective date of such final order. As part of the net energy metering proceeding, the Commission shall evaluate the six percent aggregate net metering cap and may, if appropriate, raise or remove such cap. The Commission shall enter its final order in such a proceeding no later than 12 months after it commences such proceeding, and such final order shall establish a date by which the new terms and conditions shall apply for interconnection and shall also provide that, if the terms and conditions of compensation in the final order differ from the terms and conditions available to customers before the proceeding, low-income utility customers may interconnect under whichever terms are most favorable to them.

F. Any residential eligible customer-generator or eligible agricultural customer-generator, in the service territory of a Phase II Utility who owns and operates, or contracts with other persons to own, operate, or both, an electrical generating facility with a capacity that exceeds 10 15 kilowatts shall pay to its supplier, in addition to any other charges authorized by law, a monthly standby charge. The amount of the standby charge and the terms and conditions under which it is assessed shall be in accordance with a methodology developed by the supplier and approved by the Commission. The Commission shall approve a supplier's proposed standby charge methodology if it finds that the standby charges collected from all such eligible customer-generators and eligible agricultural customer-generators allow the supplier to recover only the portion of the supplier's infrastructure costs that are properly associated with serving such eligible customer-generators or eligible agricultural customer-generators. Such an eligible customer-generator or eligible agricultural customer-generator shall not be liable for a standby charge until the date specified in an order of the Commission approving its supplier's methodology. For customers of all other investor-owned utilities, on and after July 1, 2020, standby charges are prohibited for any residential eligible customer-generator or agricultural customer-generator.

G. On and after the later of July 1, 2019, or the effective date of regulations that the Commission is required to adopt pursuant to § 56-594.01, (i) net energy metering in the service territory of each electric cooperative shall be conducted as provided in a program implemented pursuant to § 56-594.01 and (ii) the provisions of this section shall not apply to net energy metering in the service territory of an electric cooperative except as provided in § 56-594.01.

H. The Commission may adopt such rules or establish such guidelines as may be necessary for its general administration of this section.

I. When the Commission conducts a net energy metering proceeding, it shall:

1. Investigate and determine the costs and benefits of the current net energy metering program;

2. Establish an appropriate netting measurement interval for a successor tariff that is just and reasonable in light of the costs and benefits of the net metering program in aggregate, and applicable to new requests for net energy metering service; and

3. Determine a specific avoided cost for customer-generators, the different type of customer-generator technologies where the Commission deems it appropriate, and establish the methodology for determining the compensation rate for any net excess generation determined according to the applicable net measurement interval for any new tariff.

J. In evaluating the costs and benefits of the net energy metering program, the Commission shall consider:

1. The aggregate impact of customer-generators on the electric utility's long-run marginal costs of generation, distribution, and transmission;

2. The cost of service implications of customer-generators on other customers within the same class, including an evaluation of whether customer-generators provide an adequate rate of return to the electrical utility compared to the otherwise applicable rate class when, for analytical purposes only, examined as a separate class within a cost of service study;

3. The direct and indirect economic impact of the net energy metering program to the Commonwealth; and

4. Any other information it deems relevant, including environmental and resilience benefits of customer-generator facilities.

K. Notwithstanding the provisions of this section, § 56-585.1:8, or any other provision of law to the contrary, any locality that is a nonjurisdictional customer of a Phase II Utility, as defined in § 56-585.1:3, and is in Planning District Eight with a population greater than 1 million may (i) install solar-powered or wind-powered electric generation facilities with a rated capacity not exceeding five megawatts, whether the facilities are owned by the locality or owned and operated by a third party pursuant to a contract with the locality, on any locality-owned site within the locality and (ii) credit the electricity generated at any such facility as directed by the governing body of the locality to any one or more of the metered accounts of buildings or other facilities of the locality or the locality's public school division that are located within the locality, without regard to whether the buildings and facilities are located at the same site where the electric generation facility is located or at a site contiguous thereto. The amount of the credit for such electricity to the metered accounts of the locality or its public school division shall be identical, with respect to the rate structure, all retail rate components, and monthly charges, to the amount the locality or public school division would otherwise be charged for such amount of electricity under its contract with the public utility, without the assessment by the public utility of any distribution charges, service charges, or fees in connection with or arising out of such crediting.

§ 67-102. Commonwealth Energy Policy.

A. To achieve the objectives enumerated in § 67-101, it shall be the policy of the Commonwealth to:

1. Support research and development of, and promote the use of, renewable energy sources;

2. Ensure that the combination of energy supplies and energy-saving systems are sufficient to support the demands of economic growth;

3. Promote research and development of clean coal technologies, including but not limited to integrated gasification combined cycle systems;

4. Promote cost-effective conservation of energy and fuel supplies;

5. Ensure the availability of affordable natural gas throughout the Commonwealth by expanding Virginia's natural gas distribution and transmission pipeline infrastructure; developing coalbed methane gas resources and methane hydrate resources; encouraging the productive use of landfill gas; and siting one or more liquefied natural gas terminals;

6. Promote the generation of electricity through technologies that do not contribute to greenhouse gases and global warming;

7. Facilitate the development of new, and the expansion of existing, petroleum refining facilities within the Commonwealth;

8. Promote the use of motor vehicles that utilize alternate fuels and are highly energy efficient;

9. Support efforts to reduce the demand for imported petroleum by developing alternative technologies, including but not limited to the production of synthetic and hydrogen-based fuels, and the infrastructure required for the widespread implementation of such technologies;

10. Promote the sustainable production and use of biofuels produced from silvicultural and agricultural crops grown in the Commonwealth, and support the delivery infrastructure needed for statewide distribution to consumers;

11. Ensure that development of new, or expansion of existing, energy resources or facilities does not have a disproportionate adverse impact on economically disadvantaged or minority communities; and

12. Ensure that energy generation and delivery systems that may be approved for development in the Commonwealth, including liquefied natural gas and related delivery and storage systems, should be located so as to minimize impacts to pristine natural areas and other significant onshore natural resources, and as near to compatible development as possible; and

13. Support the distributed generation of renewable electricity by:

a. Encouraging private sector investments in distributed renewable energy;

b. Increasing the security of the electricity grid by supporting distributed renewable energy projects with the potential to supply electric energy to critical facilities during a widespread power outage; and

c. Augmenting the exercise of private property rights by landowners desiring to generate their own energy from renewable energy sources on their lands.

B. The elements of the policy set forth in subsection A shall be referred to collectively in this title as the Commonwealth Energy Policy.

C. All agencies and political subdivisions of the Commonwealth, in taking discretionary action with regard to energy issues, shall recognize the elements of the Commonwealth Energy Policy and where appropriate, shall act in a manner consistent therewith.

D. The Commonwealth Energy Policy is intended to provide guidance to the agencies and political subdivisions of the Commonwealth in taking discretionary action with regard to energy issues, and shall not be construed to amend, repeal, or override any contrary provision of applicable law. The failure or refusal of any person to recognize the elements of the Commonwealth Energy Policy, to act in a manner consistent with the Commonwealth Energy Policy, or to take any other action whatsoever, shall not create any right, action, or cause of action or provide standing for any person to challenge the action of the Commonwealth or any of its agencies or political subdivisions.

2. That § 1 of the first enactment of Chapters 358 and 382 of the Acts of Assembly of 2013, as amended by Chapter 803 of the Acts of Assembly of 2017, is amended and reenacted as follows:

§ 1. That the State Corporation Commission (Commission) shall conduct pilot programs under which a person that owns or operates a solar-powered or wind-powered electricity generation facility located on premises owned or leased by an eligible customer-generator, as defined in § 56-594 of the Code of Virginia, shall be permitted to sell the electricity generated from such facility exclusively to such eligible customer-generator under a power purchase agreement used to provide third party financing of the costs of such a renewable generation facility (third party power purchase agreement), subject to the following terms, conditions, and restrictions:

a. A Notwithstanding subsection G of § 56-580 of the Code of Virginia or any other provision of law, a pilot program shall be conducted within the certificated service territory of each investor-owned electric utility other than a utility described in subsection G of § 56-580 of the Code of Virginia ("Pilot Utility"), provided that within the certificated service territory of an investor-owned utility that was not bound by a rate case settlement adopted by the Commission that extended in its application beyond January 1, 2002, nonprofit, private institutions of higher education as defined in § 23.1-100 of the Code of Virginia that are not being served by generation provided under subdivision A 5 of § 56-577 of the Code of Virginia shall be deemed to be customer-generators eligible to participate in the pilot program;

b. The aggregated capacity of all generation facilities that are subject to such third party power purchase agreements at any time during the pilot program shall not exceed 50 500 megawatts for Virginia jurisdictional customers and 500 megawatts for Virginia nonjurisdictional customers for an investor-owned utility that was bound by a rate case settlement adopted by the Commission that extended in its application beyond January 1, 2002, or seven 40 megawatts for an investor-owned utility that was not bound by a rate case settlement adopted by the Commission that extended in its application beyond January 1, 2002. Such limitation on the aggregated capacity of such facilities shall constitute a portion of the existing limit of one six percent of each Pilot Utility's adjusted Virginia peak-load forecast for the previous year that is available to eligible customer-generators pursuant to subsection E of § 56-594 of the Code of Virginia. Notwithstanding any provision of this act that incorporates provisions of § 56-594, the seller and the customer shall elect either to (i) enter into their third party power purchase agreement subject to the conditions and provisions of the Pilot Utility's net energy metering program under § 56-594 or (ii) provide that electricity generated from the generation facilities subject to the third party power purchase agreement will not be net metered under § 56-594, provided that an election not to net meter under § 56-594 shall not exempt the third party power purchase agreement and the parties thereto from the requirements of this act that incorporate provisions of § 56-594;

c. A solar-powered or wind-powered generation facility with a capacity of no less than 50 kilowatts and no more than one megawatt three megawatts shall be eligible for a third party power purchase agreement under the a pilot program; however, if the customer under such agreement is an entity with tax-exempt status in accordance with § 501(c) of the Internal Revenue Code of 1954, as amended, then such facility is eligible for the pilot program even if it does not meet the 50 kilowatts minimum size requirement. The maximum generation capacity of one megawatt three megawatts shall not affect the limits on the capacity of electrical generating capacities of 20 25 kilowatts for residential customers and 500 kilowatts three megawatts for nonresidential customers set forth in subsection B of § 56-594 of the Code of Virginia, which limitations shall continue to apply to net energy metering generation facilities regardless of whether they are the subject of a third party power purchase agreement under the pilot program;

d. A generation facility that is the subject of a third party power purchase agreement under the pilot program shall serve only one customer, and a third party power purchase agreement shall not serve multiple customers;

e. The customer under a third party power purchase agreement under the pilot program shall be subject to the interconnection and other requirements imposed on eligible customer-generators pursuant to subsection C of § 56-594 of the Code of Virginia, including the requirement that the customer bear the reasonable costs, as determined by the Commission, of the items described in clauses (i), (ii), and (iii) of such subsection;

f. A third party power purchase agreement under the pilot program shall not be valid unless it conforms in all respects to the requirements of the pilot program conducted under the provisions of this act and unless the Commission and the Pilot Utility are provided written notice of the parties' intent to enter into a third party power purchase agreement not less than 30 days prior to the agreement's proposed effective date; and

g. An affiliate of the Pilot Utility shall be permitted to offer and enter into third party power purchase arrangements on the same basis as may any other person that satisfies the requirements of being a seller under a third party power purchase agreement under the pilot program.


HOUSE BILL NO. 1184
AMENDMENT IN THE NATURE OF A SUBSTITUTE
(Proposed by the Senate Committee on Commerce and Labor
on February 24, 2020)
(Patron Prior to Substitute--Delegate Lopez)
A BILL to amend and reenact §§ 56-594 and 67-102 of the Code of Virginia, to amend the Code of Virginia by adding sections numbered 56-1.2:2 and 56-594.3, and to repeal Chapters 358 and 382 of the Acts of Assembly of 2013, as amended by Chapter 803 of the Acts of Assembly of 2017, relating to the regulation of sales of electricity under third-party sales agreements; net energy; and the removal of other barriers to the increased implementation of distributed solar and other renewable energy in the Commonwealth.

Be it enacted by the General Assembly of Virginia:

1. That §§ 56-594 and 67-102 of the Code of Virginia are amended and reenacted and that the Code of Virginia is amended by adding sections numbered 56-1.2:2 and 56-594.3 as follows:

§ 56-1.2:2. Sale of electricity in connection with the sale of a renewable generation facility pursuant to a third-party power purchase agreement.

A. As used in this section and § 56-1.2, unless the context requires a different meaning:

"Renewable energy facility" means a facility that generates electricity derived entirely from sources of renewable energy as defined in § 56-576.

"Third-party power purchase agreement" means a power purchase agreement under which a seller sells electricity to a customer from a renewable energy facility located on premises owned or leased by a customer.

B. The sale of electricity generated at a renewable energy facility by a person that is not a public utility, public service corporation, or public service company to a customer that is purchasing or leasing the renewable energy facility shall not constitute the retail sale of electricity subject to regulation under this title.

C. The provisions of this section shall apply only to the sale of electricity in the certificated service territories of investor-owned utilities.

§ 56-594. Net energy metering provisions.

A. The Commission shall establish by regulation a program that affords eligible customer-generators the opportunity to participate in net energy metering, and a program, to begin no later than July 1, 2014, for customers of investor-owned utilities and to begin no later than July 1, 2015, and to end July 1, 2019, for customers of electric cooperatives as provided in subsection G, to afford eligible agricultural customer-generators the opportunity to participate in net energy metering. The regulations may include, but need not be limited to, requirements for (i) retail sellers; (ii) owners or operators of distribution or transmission facilities; (iii) providers of default service; (iv) eligible customer-generators; (v) eligible agricultural customer-generators; or (vi) any combination of the foregoing, as the Commission determines will facilitate the provision of net energy metering, provided that the Commission determines that such requirements do not adversely affect the public interest. On and after July 1, 2017, small agricultural generators or eligible agricultural customer-generators may elect to interconnect pursuant to the provisions of this section or as small agricultural generators pursuant to § 56-594.2, but not both. Existing eligible agricultural customer-generators may elect to become small agricultural generators, but may not revert to being eligible agricultural customer-generators after such election. On and after July 1, 2019, interconnection of eligible agricultural customer-generators shall cease for electric cooperatives only, and such facilities shall interconnect solely as small agricultural generators. For electric cooperatives, eligible agricultural customer-generators whose renewable energy generating facilities were interconnected before July 1, 2019, may continue to participate in net energy metering pursuant to this section for a period not to exceed 25 years from the date of their renewable energy generating facility's original interconnection.

B. For the purpose of this section:

"Eligible agricultural customer-generator" means a customer that operates a renewable energy generating facility as part of an agricultural business, which generating facility (i) uses as its sole energy source solar power, wind power, or aerobic or anaerobic digester gas, (ii) does not have an aggregate generation capacity of more than 500 kilowatts, (iii) is located on land owned or controlled by the agricultural business, (iv) is connected to the customer's wiring on the customer's side of its interconnection with the distributor; (v) is interconnected and operated in parallel with an electric company's transmission and distribution facilities, and (vi) is used primarily to provide energy to metered accounts of the agricultural business. An eligible agricultural customer-generator may be served by multiple meters serving the eligible agricultural customer-generator that are located at separate but contiguous the same or adjacent sites, such that the eligible agricultural customer-generator may aggregate in a single account the electricity consumption and generation measured by the meters, provided that the same utility serves all such meters. The aggregated load shall be served under the appropriate tariff.

"Eligible customer-generator" means a customer that owns and operates, or contracts with other persons to own, operate, or both, an electrical generating facility that (i) has a capacity of not more than 20 kilowatts for residential customers and not more than one megawatt three megawatts for nonresidential customers on an electrical generating facility placed in service after July 1, 2015; (ii) uses as its total source of fuel renewable energy, as defined in § 56-576; (iii) is located on the customer's premises land owned or leased by the customer and is connected to the customer's wiring on the customer's side of its interconnection with the distributor; (iv) is interconnected and operated in parallel with an electric company's transmission and distribution facilities; and (v) is intended primarily to offset all or part of the customer's own electricity requirements. In addition to the electrical generating facility size limitations in clause (i), the capacity of any generating facility installed under this section after July 1, 2015, shall not exceed the expected annual energy consumption based on the previous 12 months of billing history or an annualized calculation of billing history if 12 months of billing history is not available. Any generating facility installed under this section after July 1, 2002, may be located at the same site or an adjacent site. In addition to the electrical generating facility size limitation in clause (i), in the certificated service territory of a Phase I Utility, the capacity of any generating facility installed under this section after July 1, 2020, shall not exceed 100 percent of the expected annual energy consumption based on the previous 12 months of billing history or an annualized calculation of billing history if 12 months of billing history is not available, and in the certificated service territory of a Phase II Utility, the capacity of any generating facility installed under this section after July 1, 2020, shall not exceed 150 percent of the expected annual energy consumption based on the previous 12 months of billing history or an annualized calculation of billing history if 12 months of billing history is not available.

"Income qualifying customer" means an individual or household with an income of not more than 60 percent of the state median income or area median income, whichever is greater, based on U.S. Department of Housing and Urban Development guidelines. In addition, a person shall also be considered an income qualifying customer if he is eligible to participate in any of the following programs: the Home Energy Assistance Program; the state plan for medical assistance; the Supplemental Nutrition Assistance Programs; the Special Supplemental Nutrition Programs for Women, Infants and Children; the Housing Choice Voucher Program; the Family Access to Medical Insurance Security Plan; or Temporary Assistance for Needy Families.

"Net energy metering" means measuring the difference, over the net metering period, between (i) electricity supplied to an eligible customer-generator or eligible agricultural customer-generator from the electric grid and (ii) the electricity generated and fed back to the electric grid by the eligible customer-generator or eligible agricultural customer-generator.

"Net metering period" means the 12-month period following the date of final interconnection of the eligible customer-generator's or eligible agricultural customer-generator's system with an electric service provider, and each 12-month period thereafter.

"Small agricultural generator" has the same meaning that is ascribed to that term in § 56-594.2.

C. The Commission's regulations shall ensure that (i) the metering equipment installed for net metering shall be capable of measuring the flow of electricity in two directions and (ii) any eligible customer-generator seeking to participate in net energy metering shall notify its supplier and receive approval to interconnect prior to installation of an electrical generating facility. The electric distribution company shall have 30 days from the date of notification for residential facilities, and 60 days from the date of notification for nonresidential facilities, to determine whether the interconnection requirements have been met. Such regulations shall allocate fairly the cost of such equipment and any necessary interconnection. An eligible customer-generator's electrical generating system, and each electrical generating system of an eligible agricultural customer-generator, shall meet all applicable safety and performance standards established by the National Electrical Code, the Institute of Electrical and Electronics Engineers, and accredited testing laboratories such as Underwriters Laboratories. Beyond the requirements set forth in this section and to ensure public safety, power quality, and reliability of the supplier's electric distribution system, an eligible customer-generator or eligible agricultural customer-generator whose electrical generating system meets those standards and rules shall bear all reasonable costs of equipment required for the interconnection to the supplier's electric distribution system, including costs, if any, to (a) install additional controls, (b) perform or pay for additional tests, and (c) purchase additional liability insurance.

D. The Commission shall establish minimum requirements for contracts to be entered into by the parties to net metering arrangements. Such requirements shall protect the eligible customer-generator or eligible agricultural customer-generator against discrimination by virtue of its status as an eligible customer-generator or eligible agricultural customer-generator, and permit customers that are served on time-of-use tariffs that have electricity supply demand charges contained within the electricity supply portion of the time-of-use tariffs to participate as an eligible customer-generator or eligible agricultural customer-generator. Notwithstanding the cost allocation provisions of subsection C, eligible customer-generators or eligible agricultural customer-generators served on demand charge-based time-of-use tariffs shall bear the incremental metering costs required to net meter such customers.

E. If electricity generated by an eligible customer-generator or eligible agricultural customer-generator over the net metering period exceeds the electricity consumed by the eligible customer-generator or eligible agricultural customer-generator, the customer-generator or eligible agricultural customer-generator shall be compensated for the excess electricity if the entity contracting to receive such electric energy and the eligible customer-generator or eligible agricultural customer-generator enter into a power purchase agreement for such excess electricity. Upon the written request of the eligible customer-generator or eligible agricultural customer-generator, the supplier that serves the eligible customer-generator or eligible agricultural customer-generator shall enter into a power purchase agreement with the requesting eligible customer-generator or eligible agricultural customer-generator that is consistent with the minimum requirements for contracts established by the Commission pursuant to subsection D. The power purchase agreement shall obligate the supplier to purchase such excess electricity at the rate that is provided for such purchases in a net metering standard contract or tariff approved by the Commission, unless the parties agree to a higher rate. The eligible customer-generator or eligible agricultural customer-generator owns any renewable energy certificates associated with its electrical generating facility; however, at the time that the eligible customer-generator or eligible agricultural customer-generator enters into a power purchase agreement with its supplier, the eligible customer-generator or eligible agricultural customer-generator shall have a one-time option to sell the renewable energy certificates associated with such electrical generating facility to its supplier and be compensated at an amount that is established by the Commission to reflect the value of such renewable energy certificates. Nothing in this section shall prevent the eligible customer-generator or eligible agricultural customer-generator and the supplier from voluntarily entering into an agreement for the sale and purchase of excess electricity or renewable energy certificates at mutually-agreed upon prices if the eligible customer-generator or eligible agricultural customer-generator does not exercise its option to sell its renewable energy certificates to its supplier at Commission-approved prices at the time that the eligible customer-generator or eligible agricultural customer-generator enters into a power purchase agreement with its supplier. All costs incurred by the supplier to purchase excess electricity and renewable energy certificates from eligible customer-generators or eligible agricultural customer-generators shall be recoverable through its Renewable Energy Portfolio Standard (RPS) rate adjustment clause, if the supplier has a Commission-approved RPS plan. If not, then all costs shall be recoverable through the supplier's fuel adjustment clause. For purposes of this section, "all costs" shall be defined as the rates paid to the eligible customer-generator or eligible agricultural customer-generator for the purchase of excess electricity and renewable energy certificates and any administrative costs incurred to manage the eligible customer-generator's or eligible agricultural customer-generator's power purchase arrangements. The net metering standard contract or tariff shall be available to eligible customer-generators or eligible agricultural customer-generators on a first-come, first-served basis in each electric distribution company's Virginia service area until the rated generating capacity owned and operated by eligible customer-generators, eligible agricultural customer-generators, and small agricultural generators in the Commonwealth reaches one six percent of each electric distribution company's adjusted Virginia peak-load forecast for the previous year (the systemwide cap), and shall require the supplier to pay the eligible customer-generator or eligible agricultural customer-generator for such excess electricity in a timely manner at a rate to be established by the Commission. Within such systemwide cap, one percent of each electric distribution company's adjusted Virginia peak-load forecast for the previous year shall be reserved for income qualifying customers. The supplier shall develop, under the supervision of the State Corporation Commission, a system to allow income qualifying customers to identify themselves as eligible for the reserved income qualifying customers portion of the systemwide cap.

F. Any residential eligible customer-generator or eligible agricultural customer-generator, in the service territory of a Phase II Utility who owns and operates, or contracts with other persons to own, operate, or both, an electrical generating facility with a capacity that exceeds 10 kilowatts shall pay to its supplier, in addition to any other charges authorized by law, a monthly standby charge. The amount of the standby charge and the terms and conditions under which it is assessed shall be in accordance with a methodology developed by the supplier and approved by the Commission. The Commission shall approve a supplier's proposed standby charge methodology if it finds that the standby charges collected from all such eligible customer-generators and eligible agricultural customer-generators allow the supplier to recover only the portion of the supplier's infrastructure costs that are properly associated with serving such eligible customer-generators or eligible agricultural customer-generators. Such an eligible customer-generator or eligible agricultural customer-generator shall not be liable for a standby charge until the date specified in an order of the Commission approving its supplier's methodology.

G. On and after the later of July 1, 2019, or the effective date of regulations that the Commission is required to adopt pursuant to § 56-594.01, (i) net energy metering in the service territory of each electric cooperative shall be conducted as provided in a program implemented pursuant to § 56-594.01 and (ii) the provisions of this section shall not apply to net energy metering in the service territory of an electric cooperative except as provided in § 56-594.01.

H. A person that owns or operates a solar-powered or wind-powered electricity generation facility located on premises owned or leased by an eligible customer-generator shall be permitted to sell the electricity generated from such facility exclusively to such eligible customer-generator under a power purchase agreement used to provide third-party financing of the costs of such a renewable generation facility (third-party power purchase agreement), subject to the following terms, conditions, and restrictions:

1. In the service territory of a Phase I Utility, jurisdictional and non-jurisdictional customers' generation facilities having a capacity of no less than 50 kilowatts may be subject to a third-party power purchase agreement; the aggregated capacity of all such jurisdictional and non-jurisdictional customers' generation facilities subject to third-party power purchase agreement shall not exceed 40 megawatts. The aggregated capacity of all jurisdictional and non-jurisdictional customers' generation facilities subject to such third-party power purchase agreements in the service territory of a Phase II Utility shall not exceed 500 megawatts. For any investor-owned utility that is not a Phase I or Phase II Utility, the aggregated capacity of all customers' generation facilities having a capacity of no less than 50 kilowatts and subject to such third-party power purchase agreements in the service territory of a utility, other than a Phase I or Phase II Utility, shall not exceed 10 megawatts for jurisdictional customers, and there shall be no cap on the aggregated capacity of non-jurisdictional customers' or residential customers' generation facilities subject to third-party power purchase agreements.

2. Such limitation on the aggregated capacity of such facilities shall constitute a portion of the existing limit of six percent of each utility's adjusted Virginia peak-load forecast for the previous year that is available to eligible customer-generators pursuant to subsection E. The seller and the customer shall elect either to (i) enter into their third-party power purchase agreement subject to the conditions and provisions of the utility's net energy metering program under this section or (ii) provide that electricity generated from the generation facilities subject to the third-party power purchase agreement will not be net metered under this section, except that the customer under a third-party power purchase agreement shall, regardless of such election, be subject to the interconnection and safety requirements imposed on eligible customer-generators and eligible agricultural customer-generators.

I. For purposes of this section, the Commission shall liberally construe eligible customer-generators' rights to contract with other persons to own or operate, or both, an electrical generating facility, and such rights shall include the right to finance electrical generating facilities via leases and power purchase agreements. Nothing in this section shall be construed as (i) rendering any person that contracts with such eligible customer-generator pursuant to this section to be a public utility or a competitive service provider; (ii) imposing a requirement that such a person meet 100 percent of the load requirements for each customer account it serves; or (iii) affecting leases, power purchase agreements, or other third-party financing arrangements in effect prior to July 1, 2020.

§ 56-594.3. Third-party power purchase agreements.

A. As used in this section, unless the context requires a different meaning:

"Renewable energy facility" means a facility that generates electricity derived entirely from sources of renewable energy as defined in § 56-576.

"Seller" means a person that owns or operates a renewable energy facility located on premises owned or leased by a customer.

"Third-party power purchase agreement" means a power purchase agreement under which a seller sells electricity to a customer from a renewable energy facility located on premises owned or leased by a customer.

B. A seller shall be permitted to sell the electricity generated from a renewable energy facility exclusively to the customer on whose premises the renewable energy facility is located under a third-party power purchase agreement, subject to the following terms, conditions, and restrictions:

1. A renewable energy facility that is the subject of a third-party power purchase agreement shall serve only one customer, and a third-party power purchase agreement shall not serve multiple customers unless such customers are income qualifying customers;

2. The customer under a third-party power purchase agreement shall be subject to the interconnection and other requirements imposed on eligible customer-generators pursuant to subsection C of § 56-594, including the requirement that the customer bear the reasonable costs, as determined by the Commission, of the items described in clauses (a), (b), and (c) of subsection C of § 56-594;

3. A third-party power purchase agreement shall not be valid unless it conforms in all respects to the requirements of this section; and

4. An affiliate of an electric utility shall be permitted to offer and enter into third-party power purchase agreements on the same basis as may any other person that satisfies the requirements of being a seller under a third-party power purchase agreement.

C. Except as necessary to ensure compliance with the provisions of this section and the provisions of § 56-594 if the renewable energy facility is operated by an eligible customer-generator under a net energy metering program, the Commission shall not have jurisdiction to regulate the terms and conditions of a third-party power purchase agreement.

D. Nothing in this section shall be construed as (i) rendering any person, by virtue of its selling electric power to a customer under a third-party power purchase agreement entered into pursuant to this section, a public utility or a competitive service provider; (ii) imposing a requirement that such a person meet 100 percent of the load requirements for each retail customer account it serves; or (iii) affecting third-party power purchase agreements in effect prior to July 1, 2020.

E. The Commission may adopt such rules or establish such guidelines as may be necessary for its general administration of this section.

F. The provisions of this section shall apply only to the sale of electricity in the certificated service territories of investor-owned utilities.

§ 67-102. Commonwealth Energy Policy.

A. To achieve the objectives enumerated in § 67-101, it shall be the policy of the Commonwealth to:

1. Support research and development of, and promote the use of, renewable energy sources;

2. Ensure that the combination of energy supplies and energy-saving systems are sufficient to support the demands of economic growth;

3. Promote research and development of clean coal technologies, including but not limited to integrated gasification combined cycle systems;

4. Promote cost-effective conservation of energy and fuel supplies;

5. Ensure the availability of affordable natural gas throughout the Commonwealth by expanding Virginia's natural gas distribution and transmission pipeline infrastructure; developing coalbed methane gas resources and methane hydrate resources; encouraging the productive use of landfill gas; and siting one or more liquefied natural gas terminals;

6. Promote the generation of electricity through technologies that do not contribute to greenhouse gases and global warming;

7. Facilitate the development of new, and the expansion of existing, petroleum refining facilities within the Commonwealth;

8. Promote the use of motor vehicles that utilize alternate fuels and are highly energy efficient;

9. Support efforts to reduce the demand for imported petroleum by developing alternative technologies, including but not limited to the production of synthetic and hydrogen-based fuels, and the infrastructure required for the widespread implementation of such technologies;

10. Promote the sustainable production and use of biofuels produced from silvicultural and agricultural crops grown in the Commonwealth, and support the delivery infrastructure needed for statewide distribution to consumers;

11. Ensure that development of new, or expansion of existing, energy resources or facilities does not have a disproportionate adverse impact on economically disadvantaged or minority communities; and

12. Ensure that energy generation and delivery systems that may be approved for development in the Commonwealth, including liquefied natural gas and related delivery and storage systems, should be located so as to minimize impacts to pristine natural areas and other significant onshore natural resources, and as near to compatible development as possible; and

13. Support the distributed generation of renewable electricity by:

a. Encouraging private sector investments in distributed renewable energy;

b. Increasing the security of the electricity grid by supporting distributed renewable energy projects with the potential to supply electric energy to critical facilities during a widespread power outage; and

c. Augmenting the exercise of private property rights by landowners desiring to generate their own energy from renewable energy sources on their lands.

B. The elements of the policy set forth in subsection A shall be referred to collectively in this title as the Commonwealth Energy Policy.

C. All agencies and political subdivisions of the Commonwealth, in taking discretionary action with regard to energy issues, shall recognize the elements of the Commonwealth Energy Policy and where appropriate, shall act in a manner consistent therewith.

D. The Commonwealth Energy Policy is intended to provide guidance to the agencies and political subdivisions of the Commonwealth in taking discretionary action with regard to energy issues, and shall not be construed to amend, repeal, or override any contrary provision of applicable law. The failure or refusal of any person to recognize the elements of the Commonwealth Energy Policy, to act in a manner consistent with the Commonwealth Energy Policy, or to take any other action whatsoever, shall not create any right, action, or cause of action or provide standing for any person to challenge the action of the Commonwealth or any of its agencies or political subdivisions.

2. That Chapters 358 and 382 of the Acts of Assembly of 2013, as amended by Chapter 803 of the Acts of Assembly of 2017, are repealed.

3. That the repeal of Chapters 358 and 382 of the Acts of Assembly of 2013, as amended by Chapter 803 of the Acts of Assembly of 2017, shall not affect the validity of any third-party power purchase agreement entered into prior to July 1, 2020, under a pilot project authorized pursuant to Chapters 358 and 382 of the Acts of Assembly of 2013.

4. That when the rated generating capacity owned and operated by eligible customer-generators, eligible agricultural customer-generators, and small agricultural generators in the Commonwealth reaches 60 percent of the net metering systemwide cap provided for in § 56-594 of the Code of Virginia, as amended by this act, or the year 2025 for a Phase II Utility or the year 2024 for a Phase I Utility, whichever occurs first, the State Corporation Commission (the Commission) shall conduct a study proceeding to address (i) the appropriate rate structure for net metering customers; (ii) what net metering customers should pay to be connected to the grid; (iii) what net metering customers should pay for energy, infrastructure, and services the utility provides to the net metering customers; and (iv) what the utility should pay the net metering customers for energy that a net metering customer places on the grid. Notwithstanding the results of the solar study proceeding undertaken by the Commission, (a) for net metering customers with existing power purchase agreements entered into with a Phase I Utility or Phase II Utility before the entry of the final order of such proceeding, such power purchase agreement shall obligate the supplier to purchase excess electricity at the full retail rate, notwithstanding any rate that is provided for such purchases in a net metering standard contract or tariff approved by the Commission, unless the parties agree to a higher rate, and (b) the power purchase agreement entered into between a supplier and an income qualifying customer, as that term is defined in § 56-594 of the Code of Virginia, as amended by this act, shall obligate the supplier to purchase excess electricity at the full retail rate, notwithstanding the date of such customer's initial participation and notwithstanding any rate that is provided for such purchases in a net metering standard contract or tariff approved by the Commission, unless the parties agree to a higher rate.

HOUSE BILL NO. 1184

Offered January 8, 2020
Prefiled January 7, 2020
A BILL to amend and reenact §§ 56-1.2, 56-594, 67-102, and 67-103 of the Code of Virginia; to amend the Code of Virginia by adding sections numbered 15.2-2109.4, 56-1.2:2, 56-232.2:2, 56-585.1:11, 56-585.1:12, and 56-594.3; and to repeal Chapters 358 and 382 of the Acts of Assembly of 2013, as amended by Chapter 803 of the Acts of Assembly of 2017, relating to regulation of sales of electricity under third-party sales agreements; exempt resales of electricity by the owner of a multifamily residential building; net energy metering; installation of solar energy facilities by local governments; removal of other barriers to the increased implementation of distributed solar and other renewable energy in the Commonwealth.
Patron-- Lopez

Committee Referral Pending

Be it enacted by the General Assembly of Virginia:

1. That §§ 56-1.2, 56-594, 67-102, and 67-103 of the Code of Virginia are amended and reenacted and that the Code of Virginia is amended by adding sections numbered 15.2-2109.4, 56-1.2:2, 56-232.2:2, 56-585.1:11, 56-585.1:12, and 56-594.3 as follows:

§ 15.2-2109.4. Installation by localities of solar energy facilities; use of electricity generated.

Notwithstanding any provision of § 56-594, any locality that is a nonjurisdictional customer of a public electric utility may (i) install solar-powered electric generation facilities with a rated capacity not exceeding five megawatts, whether the facilities are owned by the locality or owned and operated by a third party pursuant to a contract with the locality, on any locality-owned site within the locality and (ii) credit the electricity generated at a facility described in clause (i) as directed by the governing body of the locality to any one or more of the metered accounts of buildings or other facilities of the locality or the locality's public school division that are located within the locality, without regard to whether the buildings and facilities are located at the same site where the electric generation facility is located or at a site contiguous thereto. The amount of the credit for such electricity to the metered accounts of the locality or its public school division shall be identical, with respect to the rate structure, all retail rate components, and monthly charges, to the amount the locality or public school division would otherwise be charged for such amount of electricity under its contract with the public utility, without the assessment by the public utility of any distribution charges, service charges, or fees in connection with or arising out of such crediting.

§ 56-1.2. Persons, localities, and school boards not designated as public utility, public service corporation, etc.

The terms public utility, public service corporation, or public service company, as used in Chapters 1 (§ 56-1 et seq.), 10 (§ 56-232 et seq.), 10.1 (§ 56-265.1 et seq.), and 10.2:1 (§ 56-265.13:1 et seq.) of this title, shall not refer to:

1. Any person who owns or operates property and provides electricity, natural gas, water, or sewer service to residents or tenants on the property, provided that (i) the electricity, natural gas, water, or sewer service provided to the residents or tenants is purchased by the person from a public utility, public service corporation, public service company, or person licensed by the Commission as a competitive provider of energy services, or a county, city or town, or other publicly regulated political subdivision or public body, (ii) the person or his agent charges to the resident or tenant on the property only that portion of the person's utility charges for the electricity, natural gas, water, or sewer service which is attributable to usage by the resident or tenant on the property, and additional service charges permitted by § 55.1-1212 or 55.1-1404, as applicable, and (iii) the person maintains three years' billing records for such charges.;

2. Any (i) person who is not a public service corporation and who provides electric vehicle charging service at retail, (ii) school board that operates retail fee-based electric vehicle charging stations on school property pursuant to § 22.1-131, (iii) locality that operates a retail fee-based electric vehicle charging station on property owned or leased by the locality pursuant to § 15.2-967.2, or (iv) board of visitors of any baccalaureate public institution of higher education that operates a retail fee-based electric vehicle charging station on the grounds of such institution pursuant to § 23.1-1301.1. The ownership or operation of a facility at which electric vehicle charging service is sold, and the selling of electric vehicle charging service from that facility, does not render such person, school board, locality, or board of visitors a public utility, public service corporation, or public service company as used in Chapters 1 (§ 56-1 et seq.), 10 (§ 56-232 et seq.), 10.1 (§ 56-265.1 et seq.), and or 10.2:1 (§ 56-265.13:1 et seq.) solely because of that sale, ownership, or operation.;

3. The Department of Conservation and Recreation when operating a retail fee-based electric vehicle charging station on property of any existing state park or similar recreational facility the Department controls pursuant to § 10.1-104.01. The ownership or operation of a facility at which electric vehicle charging service is sold, or the selling of electric vehicle charging service from that facility, does not render the Department of Conservation and Recreation a public utility, public service corporation, or public service company as used in Chapters 1 (§ 56-1 et seq.), 10 (§ 56-232 et seq.), 10.1 (§ 56-265.1 et seq.), and 10.2:1 (§ 56-265.13:1 et seq.) solely because of that sale, ownership, or operation.;

4. The Chancellor of the Virginia Community College System when operating a retail fee-based electric vehicle charging station on the grounds of any comprehensive community college pursuant to § 23.1-2908.1. The ownership or operation of a facility at which electric vehicle charging service is sold, or the selling of electric vehicle charging service from that facility, does not render the Chancellor of the Virginia Community College System a public utility, public service corporation, or public service company as used in Chapters 1 (§ 56-1 et seq.), 10 (§ 56-232 et seq.), 10.1 (§ 56-265.1 et seq.), and 10.2:1 (§ 56-265.13:1 et seq.) solely because of that sale, ownership, or operation.;

5. The Department of General Services, Department of Motor Vehicles, or Department of Transportation when operating a retail fee-based electric vehicle charging station on any property or facility that such agency controls. The ownership or operation of a facility at which electric vehicle charging service is sold, or the selling of electric vehicle charging service from that facility, does not render the agency a public utility, public service corporation, or public service company as used in Chapters 1 (§ 56-1 et seq.), 10 (§ 56-232 et seq.), 10.1 (§ 56-265.1 et seq.), and 10.2:1 (§ 56-265.13:1 et seq.) solely because of that sale, ownership, or operation.;

6. Any person that is not a public service corporation and that sells electricity generated on site entirely from sources of renewable energy as defined in § 56-576 at retail to a customer pursuant to a third-party power purchase agreement, as defined in § 56-1.2:2, if the sale of electricity is conducted pursuant to § 56-594.3. The ownership or operation of such an onsite facility generating electric energy derived entirely from sources of renewable energy from which electric energy is sold to a customer pursuant to a third-party power purchase agreement, and the selling of electric energy to such a customer from that facility, does not render the person a public utility, public service corporation, public service company, or electric utility as used in Chapters 1 (§ 56-1 et seq.), 10 (§ 56-232 et seq.), 10.1 (§ 56-265.1 et seq.), 10.2:1 (§ 56-265.13:1 et seq.), and 23 (§ 56-576 et seq.) solely because of that sale of electricity or its ownership or operation of such a generation facility; or

7. Any eligible owner that sells or offers to sell electric power to an eligible customer pursuant to § 56-585.1:8. The ownership or operation of a renewable energy facility at which electricity is generated for the purpose of sale to eligible purchasers, and the selling of electric power from that facility, pursuant to § 56-585.1:8, does not render such person a public utility, public service corporation, or public service company as used in Chapters 1 (§ 56-1 et seq.), 10 (§ 56-232 et seq.), 10.1 (§ 56-265.1 et seq.), 10.2:1 (§ 56-265.13:1 et seq.), and 23 (§ 56-576 et seq.) solely because of that sale, ownership, or operation.

§ 56-1.2:2. Sale of electricity in connection with the sale of a solar generation facility pursuant to a third-party power purchase agreement.

A. As used in this section and §§ 56-1.2 and 56-232.2:2, unless the context requires a different meaning:

"Solar energy facility" means a facility that generates electricity derived entirely from sources of solar energy.

"Third-party power purchase agreement" means a power purchase agreement under which a seller sells electricity to a customer from a solar energy facility located on premises owned or leased by a customer.

B. The sale of electricity generated at a solar energy facility by a person that is not a public utility, public service corporation, or public service company to a customer that is purchasing or leasing the solar energy facility shall not constitute the retail sale of electricity subject to regulation under this title.

§ 56-232.2:2. Regulation of third-party power purchase agreements.

The Commission shall not regulate or prescribe the rates, charges, and fees for the sale by any person that is not a public service corporation of electric energy generated on site entirely from sources of solar energy to a customer pursuant to a third-party power purchase agreement entered into pursuant to § 56-594.3. Sales of electricity by public utilities to persons that are not public service corporations pursuant to third-party power purchase agreements shall continue to be regulated by the Commission to the same extent as are other services provided by public utilities. The Commission may adopt regulations implementing this section.

§ 56-585.1:11. Exempt sales of solar energy to occupants of eligible property.

A. As used in this section:

"Eligible owner" means the fee simple owner of an eligible property.

"Eligible property" means real estate located in the Commonwealth that is either (i) a multifamily residential building consisting of rental units or (ii) common elements of a condominium as such terms are defined in § 55.1-1900.

"Eligible purchaser" means (i) a tenant occupying a rental unit in a multifamily residential building that qualifies as eligible property or (ii) the owner, or a person renting from the owner, of a condominium unit in a condominium of which common elements qualify as eligible property.

"Power purchase agreement" means an agreement under which an eligible owner sells electricity generated from a solar energy facility to an eligible purchaser.

"Solar energy facility" means a solar-powered electric generation facility that is installed on (i) eligible property or (ii) a lot or parcel that is (a) owned by the eligible owner and (b) adjacent to the eligible property.

"Utility" means the investor-owned electric utility or cooperative electric utility that is the certificated service provider for the eligible property.

B. Notwithstanding any provision of this title to the contrary, an eligible owner shall be permitted to sell the electricity generated from a solar energy facility exclusively to eligible purchasers under power purchase agreements, subject to the following:

1. The power purchase agreement provides only for the sale of electric power to meet the needs of an eligible purchaser in the eligible purchaser's rental unit or condominium unit, as applicable, or for charging an eligible purchaser's electric vehicle regularly garaged or parked at the multifamily residential building or condominium, as applicable;

2. All rates, charges, fees, and other terms of the sale and delivery of electric power by an eligible owner to an eligible purchaser shall be determined by the terms of the power purchase agreement and shall not be subject to regulation by the Commission; and

3. A utility shall not charge an eligible purchaser rates and charges for service provided to the eligible purchaser in order to supplement purchases under a power purchase agreement that exceed its generally applicable rates and charges for electricity and related services provided by the utility to customers of the same class.

C. Nothing in this section shall be construed as rendering an eligible owner, by virtue of its selling electric power to an eligible purchaser under a power purchase agreement entered into pursuant to this section, a public utility, public service company, public service corporation, or competitive service provider that is subject to the provisions of this title.

§ 56-585.1:12. Installation by public bodies of solar energy facilities; use of electricity generated.

A. As used in this section, "public body" means any park authority, any public recreational facilities authority, any soil and water conservation district, any community development authority formed pursuant to Article 6 (§ 15.2-5152 et seq.) of Chapter 51 of Title 15.2, or any authority created under the Virginia Water and Waste Authorities Act (§ 15.2-5100 et seq.).

B. Notwithstanding any provision of § 56-594, any public body that is a nonjurisdictional customer of an electric utility may (i) install solar-powered electric generation facilities with a rated capacity not exceeding five megawatts, whether the facilities are owned by the public body or owned and operated by a third party pursuant to a contract with the public body, on any site owned by the public body and (ii) credit the electricity generated at a facility described in clause (i) as directed by the public body to any one or more of the metered accounts of buildings or other facilities of the public body that are located on any property owned by the public body, without regard to whether the buildings and facilities are located at the same site where the electric generation facility is located or at a site contiguous thereto. The amount of the credit for such electricity to the metered accounts of the public body shall be identical, with respect to the rate structure, all retail rate components, and monthly charges, to the amount the public body would otherwise be charged for such amount of electricity under its contract with the public utility, without the assessment by the public utility of any distribution charges, service charges, or fees in connection with or arising out of such crediting.

§ 56-594. Net energy metering provisions.

A. The Commission shall establish by regulation a program that affords eligible customer-generators the opportunity to participate in net energy metering, and a program, to begin no later than July 1, 2014, for customers of investor-owned utilities and to begin no later than July 1, 2015, and to end July 1, 2019, for customers of electric cooperatives as provided in subsection G F, to afford eligible agricultural customer-generators the opportunity to participate in net energy metering. The regulations may include, but need not be limited to, requirements for (i) retail sellers; (ii) owners or operators of distribution or transmission facilities; (iii) providers of default service; (iv) eligible customer-generators; (v) eligible agricultural customer-generators; or (vi) any combination of the foregoing, as the Commission determines will facilitate the provision of net energy metering, provided that the Commission determines that such requirements do not adversely affect the public interest. On and after July 1, 2017, small agricultural generators or eligible agricultural customer-generators may elect to interconnect pursuant to the provisions of this section or as small agricultural generators pursuant to § 56-594.2, but not both. Existing eligible agricultural customer-generators may elect to become small agricultural generators, but may not revert to being eligible agricultural customer-generators after such election. On and after July 1, 2019, interconnection of eligible agricultural customer-generators shall cease for electric cooperatives only, and such facilities shall interconnect solely as small agricultural generators. For electric cooperatives, eligible agricultural customer-generators whose renewable energy generating facilities were interconnected before July 1, 2019, may continue to participate in net energy metering pursuant to this section for a period not to exceed 25 years from the date of their renewable energy generating facility's original interconnection.

B. For the purpose of this section:

"Eligible agricultural customer-generator" means a customer that operates a renewable energy generating facility as part of an agricultural business, which generating facility (i) uses as its sole energy source solar power, wind power, or aerobic or anaerobic digester gas, (ii) does not have an aggregate generation capacity of more than 500 kilowatts, (iii) is located on land owned or controlled by the agricultural business, (iv) is connected to the customer's wiring on the customer's side of its interconnection with the distributor; (v) is interconnected and operated in parallel with an electric company's transmission and distribution facilities, and (vi) is used primarily to provide energy to metered accounts of the agricultural business. An eligible agricultural customer-generator may be served by multiple meters that are located at separate but contiguous sites, whether or not contiguous, such that the eligible agricultural customer-generator may aggregate in a single account the electricity consumption and generation measured by the meters, provided that the same utility serves all such meters. The aggregated load shall be served under the appropriate tariff.

"Eligible customer-generator" means a customer that owns and operates, or contracts with other persons to own, operate, or both, an electrical generating facility that (i) has a capacity of not more than 20 kilowatts for residential customers and not more than one megawatt three megawatts for nonresidential customers on an electrical generating facility placed in service after July 1, 2015; (ii) uses as its total source of fuel renewable energy, as defined in § 56-576; (iii) is located on the customer's premises land owned or leased by the customer and is connected to the customer's wiring on the customer's side of its interconnection with the distributor; (iv) is interconnected and operated in parallel with an electric company's transmission and distribution facilities; and (v) is intended primarily to offset all or part of the customer's own electricity requirements. In addition to the electrical generating facility size limitations in clause (i), the capacity of any generating facility installed under this section after July 1, 2015, shall not exceed the expected annual energy consumption based on the previous 12 months of billing history or an annualized calculation of billing history if 12 months of billing history is not available An eligible customer-generator may be served by multiple meters serving the same eligible customer-generator that are located at the same site or an adjacent site, such that the eligible customer-generator may aggregate in a single account the electricity consumption and generation measured by the meters, provided that the same utility serves all such meters. The two-megawatt limitation in clause (i) on the capacity of electrical generating facilities for nonresidential customers does not apply to electrical generating facilities that are operated pursuant to § 15.2-2109.4 or 56-585.1:12.

"Net energy metering" means measuring the difference, over the net metering period, between (i) electricity supplied to an eligible customer-generator or eligible agricultural customer-generator from the electric grid and (ii) the electricity generated and fed back to the electric grid by the eligible customer-generator or eligible agricultural customer-generator.

"Net metering period" means the 12-month period following the date of final interconnection of the eligible customer-generator's or eligible agricultural customer-generator's system with an electric service provider, and each 12-month period thereafter.

"Small agricultural generator" has the same meaning that is ascribed to that term in § 56-594.2.

C. The Commission's regulations shall ensure that (i) the metering equipment installed for net metering shall be capable of measuring the flow of electricity in two directions and (ii) any eligible customer-generator seeking to participate in net energy metering shall notify its supplier and receive approval to interconnect prior to installation of an electrical generating facility. The electric distribution company shall have 30 days from the date of notification for residential facilities, and 60 days from the date of notification for nonresidential facilities, to determine whether the interconnection requirements have been met. Such regulations shall allocate fairly the cost of such equipment and any necessary interconnection. An eligible customer-generator's electrical generating system, and each electrical generating system of an eligible agricultural customer-generator, shall meet all applicable safety and performance standards established by the National Electrical Code, the Institute of Electrical and Electronics Engineers, and accredited testing laboratories such as Underwriters Laboratories. Beyond the requirements set forth in this section and to ensure public safety, power quality, and reliability of the supplier's electric distribution system, an eligible customer-generator or eligible agricultural customer-generator whose electrical generating system meets those standards and rules shall bear all reasonable costs of equipment required for the interconnection to the supplier's electric distribution system, including costs, if any, to (a) install additional controls, (b) perform or pay for additional tests, and (c) purchase additional liability insurance.

D. The Commission shall establish minimum requirements for contracts to be entered into by the parties to net metering arrangements. Such requirements shall protect the eligible customer-generator or eligible agricultural customer-generator against discrimination by virtue of its status as an eligible customer-generator or eligible agricultural customer-generator, and permit customers that are served on time-of-use tariffs that have electricity supply demand charges contained within the electricity supply portion of the time-of-use tariffs to participate as an eligible customer-generator or eligible agricultural customer-generator. Notwithstanding the cost allocation provisions of subsection C, eligible customer-generators or eligible agricultural customer-generators served on demand charge-based time-of-use tariffs shall bear the incremental metering costs required to net meter such customers.

E. If electricity generated by an eligible customer-generator or eligible agricultural customer-generator over the net metering period exceeds the electricity consumed by the eligible customer-generator or eligible agricultural customer-generator, the customer-generator or eligible agricultural customer-generator shall be compensated for the excess electricity if the entity contracting to receive such electric energy and the eligible customer-generator or eligible agricultural customer-generator enter into a power purchase agreement for such excess electricity. Upon the written request of the eligible customer-generator or eligible agricultural customer-generator, the supplier that serves the eligible customer-generator or eligible agricultural customer-generator shall enter into a power purchase agreement with the requesting eligible customer-generator or eligible agricultural customer-generator that is consistent with the minimum requirements for contracts established by the Commission pursuant to subsection D. The power purchase agreement shall obligate the supplier to purchase such excess electricity at the rate that is provided for such purchases in a net metering standard contract or tariff approved by the Commission, unless the parties agree to a higher rate. The eligible customer-generator or eligible agricultural customer-generator owns any renewable energy certificates associated with its electrical generating facility; however, at the time that the eligible customer-generator or eligible agricultural customer-generator enters into a power purchase agreement with its supplier, the eligible customer-generator or eligible agricultural customer-generator shall have a one-time option to sell the renewable energy certificates associated with such electrical generating facility to its supplier and be compensated at an amount that is established by the Commission to reflect the value of such renewable energy certificates. Nothing in this section shall prevent the eligible customer-generator or eligible agricultural customer-generator and the supplier from voluntarily entering into an agreement for the sale and purchase of excess electricity or renewable energy certificates at mutually-agreed upon prices if the eligible customer-generator or eligible agricultural customer-generator does not exercise its option to sell its renewable energy certificates to its supplier at Commission-approved prices at the time that the eligible customer-generator or eligible agricultural customer-generator enters into a power purchase agreement with its supplier. All costs incurred by the supplier to purchase excess electricity and renewable energy certificates from eligible customer-generators or eligible agricultural customer-generators shall be recoverable through its Renewable Energy Portfolio Standard (RPS) rate adjustment clause, if the supplier has a Commission-approved RPS plan. If not, then all costs shall be recoverable through the supplier's fuel adjustment clause. For purposes of this section, "all costs" shall be defined as the rates paid to the eligible customer-generator or eligible agricultural customer-generator for the purchase of excess electricity and renewable energy certificates and any administrative costs incurred to manage the eligible customer-generator's or eligible agricultural customer-generator's power purchase arrangements. The net metering standard contract or tariff shall be available to eligible customer-generators or eligible agricultural customer-generators on a first-come, first-served basis in each electric distribution company's Virginia service area until the rated generating capacity owned and operated by eligible customer-generators, eligible agricultural customer-generators, and small agricultural generators in the Commonwealth reaches one 10 percent of each electric distribution company's adjusted Virginia peak-load forecast for the previous year (the systemwide cap), and shall require the supplier to pay the eligible customer-generator or eligible agricultural customer-generator for such excess electricity in a timely manner at a rate to be established by the Commission.

F. Any residential eligible customer-generator or eligible agricultural customer-generator who owns and operates, or contracts with other persons to own, operate, or both, an electrical generating facility with a capacity that exceeds 10 kilowatts shall pay to its supplier, in addition to any other charges authorized by law, a monthly standby charge. The amount of the standby charge and the terms and conditions under which it is assessed shall be in accordance with a methodology developed by the supplier and approved by the Commission. The Commission shall approve a supplier's proposed standby charge methodology if it finds that the standby charges collected from all such eligible customer-generators and eligible agricultural customer-generators allow the supplier to recover only the portion of the supplier's infrastructure costs that are properly associated with serving such eligible customer-generators or eligible agricultural customer-generators. Such an eligible customer-generator or eligible agricultural customer-generator shall not be liable for a standby charge until the date specified in an order of the Commission approving its supplier's methodology.

G. On and after the later of July 1, 2019, or the effective date of regulations that the Commission is required to adopt pursuant to § 56-594.01, (i) net energy metering in the service territory of each electric cooperative shall be conducted as provided in a program implemented pursuant to § 56-594.01 and (ii) the provisions of this section shall not apply to net energy metering in the service territory of an electric cooperative except as provided in § 56-594.01.

§ 56-594.3. Third-party power purchase agreements.

A. As used in this section, unless the context requires a different meaning:

"Seller" means a person that owns or operates a renewable energy facility located on premises owned or leased by a customer.

"Solar energy facility" means a facility that generates electricity derived entirely from sources of solar energy.

"Third-party power purchase agreement" means a power purchase agreement under which a seller sells electricity to a customer from a solar energy facility located on premises owned or leased by a customer.

B. A seller shall be permitted to sell the electricity generated from a solar energy facility exclusively to the customer on whose premises the solar energy facility is located under a third-party power purchase agreement, subject to the following terms, conditions, and restrictions:

1. A solar energy facility that is the subject of a third-party power purchase agreement shall serve only one customer, and a third-party power purchase agreement shall not serve multiple customers;

2. The customer under a third-party power purchase agreement shall be subject to the interconnection and other requirements imposed on eligible customer-generators pursuant to subsection C of § 56-594, including the requirement that the customer bear the reasonable costs, as determined by the Commission, of the items described in clauses (a), (b), and (c) of subsection C of § 56-594;

3. A third-party power purchase agreement shall not be valid unless it conforms in all respects to the requirements of this section; and

4. An affiliate of an electric utility shall be permitted to offer and enter into third-party power purchase agreements on the same basis as may any other person that satisfies the requirements of being a seller under a third-party power purchase agreement.

C. Except as necessary to ensure compliance with the provisions of this section and the provisions of § 56-594 if the solar energy facility is operated by an eligible customer-generator under a net energy metering program, the Commission shall not have jurisdiction to regulate the terms and conditions of a third-party power purchase agreement.

D. Nothing in this section shall be construed as (i) rendering any person, by virtue of its selling electric power to a customer under a third-party power purchase agreement entered into pursuant to this section, a public utility or a competitive service provider; (ii) imposing a requirement that such a person meet 100 percent of the load requirements for each retail customer account it serves; or (iii) affecting third-party power purchase agreements in effect prior to July 1, 2020.

E. The Commission may adopt such rules or establish such guidelines as may be necessary for its general administration of this section.

§ 67-102. Commonwealth Energy Policy.

A. To achieve the objectives enumerated in § 67-101, it shall be the policy of the Commonwealth to:

1. Support research and development of, and promote the use of, renewable energy sources;

2. Ensure that the combination of energy supplies and energy-saving systems are sufficient to support the demands of economic growth;

3. Promote research and development of clean coal technologies, including but not limited to integrated gasification combined cycle systems;

4. Promote cost-effective conservation of energy and fuel supplies;

5. Ensure the availability of affordable natural gas throughout the Commonwealth by expanding Virginia's natural gas distribution and transmission pipeline infrastructure; developing coalbed methane gas resources and methane hydrate resources; encouraging the productive use of landfill gas; and siting one or more liquefied natural gas terminals;

6. Promote the generation of electricity through technologies that do not contribute to greenhouse gases and global warming;

7. Facilitate the development of new, and the expansion of existing, petroleum refining facilities within the Commonwealth;

8. Promote the use of motor vehicles that utilize alternate fuels and are highly energy efficient;

9. Support efforts to reduce the demand for imported petroleum by developing alternative technologies, including but not limited to the production of synthetic and hydrogen-based fuels, and the infrastructure required for the widespread implementation of such technologies;

10. Promote the sustainable production and use of biofuels produced from silvicultural and agricultural crops grown in the Commonwealth, and support the delivery infrastructure needed for statewide distribution to consumers;

11. Ensure that development of new, or expansion of existing, energy resources or facilities does not have a disproportionate adverse impact on economically disadvantaged or minority communities; and

12. Ensure that energy generation and delivery systems that may be approved for development in the Commonwealth, including liquefied natural gas and related delivery and storage systems, should be located so as to minimize impacts to pristine natural areas and other significant onshore natural resources, and as near to compatible development as possible; and

13. Support the distributed generation of solar electricity by:

a. Encouraging private sector investments in distributed solar energy;

b. Increasing the security of the electricity grid by supporting distributed solar energy projects with the potential to supply electric energy to critical facilities during a widespread power outage; and

c. Augmenting the exercise of private property rights by landowners desiring to generate their own electricity from solar energy sources located on their property.

B. The distributed generation of solar electricity is in the public interest, and the State Corporation Commission shall so find if required to make a finding regarding whether such construction or purchase is in the public interest.

C. The elements of the policy set forth in subsection subsections A and B shall be referred to collectively in this title as the Commonwealth Energy Policy.

C. D. All agencies and political subdivisions of the Commonwealth, in taking discretionary action with regard to energy issues, shall recognize the elements of the Commonwealth Energy Policy and where appropriate, shall act in a manner consistent therewith.

D. E. The Commonwealth Energy Policy is intended to provide guidance to the agencies and political subdivisions of the Commonwealth in taking discretionary action with regard to energy issues, and shall not be construed to amend, repeal, or override any contrary provision of applicable law. The failure or refusal of any person to recognize the elements of the Commonwealth Energy Policy, to act in a manner consistent with the Commonwealth Energy Policy, or to take any other action whatsoever, shall not create any right, action, or cause of action or provide standing for any person to challenge the action of the Commonwealth or any of its agencies or political subdivisions.

§ 67-103. Role of local governments in achieving objectives of the Commonwealth Energy Policy.

In the development of any local ordinance addressing the siting of renewable energy facilities that generate electricity from wind or solar resources, the ordinance shall:

1. Be consistent with the provisions of the Commonwealth Energy Policy pursuant to subsection C D of § 67-102;

2. Provide reasonable criteria to be addressed in the siting of any renewable energy facility that generates electricity from wind and solar resources. The criteria shall provide for the protection of the locality in a manner consistent with the goals of the Commonwealth to promote the generation of energy from wind and solar resources; and

3. Include provisions establishing reasonable requirements upon the siting of any such renewable energy facility, including provisions limiting noise, requiring buffer areas and setbacks, and addressing generation facility decommissioning.

Any measures required by the ordinance shall be consistent with the locality's existing ordinances.

2. That Chapters 358 and 382 of the Acts of Assembly of 2013, as amended by Chapter 803 of the Acts of Assembly of 2017, are repealed.

3. That the repeal of Chapters 358 and 382 of the Acts of Assembly of 2013, as amended by Chapter 803 of the Acts of Assembly of 2017, shall not affect the validity of any third-party power purchase agreement entered into prior to July 1, 2019, under a pilot project authorized pursuant to Chapters 358 and 382 of the Acts of Assembly of 2013, as amended by Chapter 803 of the Acts of Assembly of 2017.